08. Unit Lifting Procedures
08.01. Crane Lifting Method
WARNING
WH&S regulations must be observed and will take precedence during lifting process.
NOTE
Crane lifting is recommended over forklift method.
Provide rubber pads
to prevent damage
to the unit
Provide rubb
er
pads t
o pr
event
damag
e
to the unit
Provide rubber pads
to prevent damage
to the unit
Connect the loop ends
of slings into shackle
SIZE: Ø 26 mm (4 - Off)
Attach Dee Shackles to connect slings
SLING POINT
Equipment Required For Crane Lifting:
- 4 x Shackles (must be load rated shackles)
- 2 x Nylon Slings
- Spreader bar
NOTE
Refer to catalogue for unit weight before selecting shackles.
Procedure:
1. Use 4 x Bow or Dee shackles to connect the lifting holes.
2. Slip nylon slings through all shackles.
3. Ensure slings are protected by rubber pads or similar if slings are draped across unit edges, corners, or air grilles . This
will prevent the unit from being damaged during lifting.
4. SPREADER BAR must be used when lifting the unit.
5. Test lift the unit to determine exact unit balance and stability before hoisting it to the installation location.