Figure 10: Wall-Mount, Interior View
Locate each ACE2 unit as close as possible to the controllable elements, the Regulator, the Generator etc. Mount the CVM and
the IRM board (if present) separately from the ACE2.
Mount the Wall-mount ACE2 flush against a wall or on U-channels that support all four corners of the enclosure.
5.2.1 ACE2 Cabling Entry
Note
The ACE2 enclosure is designed to be replaced easily without having to remove the mounting hardware. Follow these
instructions:
1. Position the enclosure flush on its mounting surface.
Level the enclosure and open the lid. Mark or transfer punch the location of the 3/8” diameter holes in each corner of the
enclosure shown in
2. Remove the ACE2 unit and drill the marked holes.
Insert anchor hardware as required. DO NOT DRILL THOUGH THE BOX. Drilling chips and debris can not fall into the
enclosure.
3. Carefully open the lid of the enclosure.
Use ¼-20 x 1.0-inch long screws, flat washers, and lock washers to fasten the enclosure to the wall or to rails.
4. Mount the enclosure using the top two holes then install the hardware for the bottom two holes.
5. Attach all conduits to the bottom or to the top access plate ONLY.
6. Protect all equipment inside the ACE2 enclosure while installing conduit.
Note
All conduit and wiring must only enter the ACE2 enclosure through the bottom or the top access plate. This
facilitates quick maintenance and replacement of the ACE2 unit.
Advanced Control Equipment (ACE2)
Installation
20
Copyright
©
ADB Safegate, All Rights Reserved
Summary of Contents for ACE2
Page 1: ...Advanced Control Equipment ACE2 User Manual 96A0357 Rev G 2019 11 08 ...
Page 2: ......
Page 18: ...Advanced Control Equipment ACE2 Introduction 12 Copyright ADB Safegate All Rights Reserved ...
Page 42: ...Advanced Control Equipment ACE2 Parts 36 Copyright ADB Safegate All Rights Reserved ...
Page 46: ......