4.0 Replacing a stand-alone RELIANCE Intelligent Lighting Master
1. Before exchanging a RELIANCE IL Master, record its technical information.
2. Switch off the RELIANCE IL Master to be replaced with the Power Switch and its associated series circuit and disconnect it
from the mains power supply by removing the fuses of the Constant current regulator.
3. Pull out the cut-out for the series circuit, if available. If possible earth ground the series circuit and wait 5 minutes until the
circuit is fully discharged.
Switch off any ground fault detection devices (IRMS) which may be connected to this circuit.
Note
For all work on the devices, follow the
4. Removing the RELIANCE IL Master
First separate the high-voltage connections “FIELD” and “CCR” on the RELIANCE IL Master at their cable plug connections
and pull the rubber connector out of the POWER socket.
Open the ground connection by loosening the nut on the earth ground screw of the RELIANCE IL Master. Remove
connected network links on Ethernet 0, and Ethernet 1.
Now, physically remove the RELIANCE IL Master from the control cabinet.
a) Loosen and slide back the top cover of the old master.
b) Remove the CF cord from the SBC.
c) Loosen and slide back the top cover pf the new master.
d) Swap the CF card in the new master with the one from the old master.
5. Install the new RELIANCE IL Master according to the
Installation of stand-alone RELIANCE IL Masters
.
4.1 Modes of Operation
More information about the modes of operation contact your ADB SAFEGATE representative.
4.2 State on Delivery
The RELIANCE Intelligent Lighting (IL) Master is delivered with no default IP address set for either Ethernet interfaces Eth0 (Eth
0) and Eth1 (Eth 1). The address must be entered by the user via the RELIANCE IL PC.
The following are the states of the RELIANCE IL Master:
•
Boot Step
•
Offline
•
Provisioning
•
Operational
•
Failsafe
•
Critical Fault
4.3 Operating Mode
4.4 HMI Display Screen
Header: The header is always displayed on every screen and shows the Master ID, Master Name, and a lightning bolt
indicating if the circuit is energized or not.
96A0480, Rev. B, 2019/12/06
23
Copyright
©
ADB Safegate, All Rights Reserved
Summary of Contents for RELIANCE Intelligent Lighting Platform II
Page 2: ......
Page 38: ...RELIANCE Intelligent Lighting Platform II Parts 32 Copyright ADB Safegate All Rights Reserved ...
Page 42: ......