that the fan wheel is clean.
13.6 Venting and Air Intake Pipe
Inspect all venting and air intake pipe. Ensure that
all seams are sealed and suspension points secure.
Repair suspension points if any part of the venting
or combustion air pipe is sagging. Check to make
sure any insulation is not missing or in poor
condition. Replace as necessary. Check all venting
and air intake components to ensure they are in
good condition, gas tight and corrosion-free.
13.7 Maintenance Checklist
Installation Code and Annual Inspections:
All
installation and service of ADDISON
®
equipment
must be performed by a contractor qualified in the
installation and service equipment sold and supplied
by Addison and conform to all requirements set forth
in the ADDISON
®
manuals and all applicable
governmental authorities pertaining to the
installation, service, operation and labeling of the
equipment.
To help facilitate optimum performance and safety,
Addison recommends that a qualified contractor
conduct, at a minimum, annual inspections of your
ADDISON
®
equipment and perform service where
necessary, using only replacement parts sold and
supplied by Addison.
Annual Fall Start Up
Follow entire start-up procedure at this time and check control settings and
operation.
The Vicinity of the Heater
Do not store or use flammable objects, liquids or vapors near the heater.
Immediately remove these items if they are present.
See Page 6, Section 3
.
Vehicles and Other
Objects
Maintain the clearances to combustibles.
Do not hang anything from, or place anything on, the heater.
Make sure nothing is lodged in between the heat exchanger tubes.
Immediately remove objects in violation of the clearances to combustibles.
See Page 7, Section 4
.
Vent Pipe/Terminals
Venting must be intact. Using a flashlight, look for obstructions, cracks on the
pipe, gaps in the sealed areas or corrosion.
The area must be free of dirt and dust.
Remove any carbon deposits or scale using a wire brush.
If the vent terminal has a screen built in, remove any dirt, dust or deposits
from the screen.
See Page 11, Section 7
through Page 17, Section 8
.
Cabinet Exterior
After installation, touch up scratches. Periodic painting should be done there-
after as required. Warning labels and logo labels should be legible and accu-
rate. Please contact Addison or ADDISON
®
independent distributor if you
need replacement warning labels or logo labels.
See Page 2, Figure 1
through Page 4, Figure 3
.
Combustion Air Intake
Pipe
Intake pipe and inlet must be intact. Look for obstructions, cracks on the pipe,
gaps in the sealed areas or corrosion.
The area must be free of dirt and dust.
Clean and reinstall as required.
See Page 17, Section 8
.
Summary of Contents for UHD150
Page 2: ......
Page 4: ......
Page 8: ......
Page 27: ...SECTION 9 GAS PIPING 19 of 55 Figure 13 Gas Connection...
Page 47: ...SECTION 14 TROUBLESHOOTING 39 of 55 14 1 General...
Page 62: ...UHD STANDARD DUCT FURNACE INSTALLATION OPERATION AND SERVICE MANUAL 54 of 55...
Page 64: ......
Page 65: ......
Page 66: ......
Page 67: ......
Page 68: ......