Wiring Connections
The procedures in this practice for bringing in power and data to the cabinet are supplemental
to Emerson document 631-205-071, which provides detailed information and corresponding
illustrations.
WARNING
Ensure AC power is disconnected at the source and tagged “Out of
Service” prior to making power connections.
AC Power can cause injury or death. Observe all safety precautions
as specified by local building codes and the National Electrical
Code (NEC). A licensed electrician should perform all installation
procedures. If local building codes are different from those in this
section, follow local codes. Before installation, bond the AC
grounding electrode system to an AC main service power neutral/
ground bus. Contact your local power company or the appropriate
local personnel for information about codes or restrictions for your
installation.
AC Load Center Distribution
Before installing AC power, ensure that the AC ground system is installed. The ground system
must be in compliance with local practices and building codes. For detailed installation and
wiring instructions of the AC ground system, refer to “Section 3, AC Power” in Emerson
document 631-205-071.
All internal AC power wiring is factory installed. The AC Load Center receives 120-volt,
60-amp service from the local utility, hard wired into the AC Load Center via a 30-amp supply
side main circuit breaker. The AC distribution to cabinet AC loads is via four load side circuit
breakers The AC Load Center has capacity for eight circuit breakers.
The AC circuit breakers installed in the AC Load Center are sized according to the current
requirements of the equipment in the circuit. In the event that any breaker becomes defective
and must be replaced, replace with an AC breaker of the same current rating.
outlines
circuit breaker assignments and current ratings.
Note: Circuit breakers 6 through 8 are not connected.
Table 5. Circuit Breaker Assignments and Current Ratings
AC Load Center
Designation
Amp Rating
CB1
Main Supply
30
CB2
Rectifier #1 and #3
15
CB3
Rectifier #2
15
CB4
GFI Outlet
15
CB5
Battery Heater
10