Acceptance Test Procedure ATP-601
1.
Verify DSX-1 Wiring
Use the procedure outlined in DLP-720 to verify the wiring of each shelf to the
DSX-1 cross connect. If a wiring problem is found, correct the problem before
proceeding.
2.
Verify MDF Wiring
Use the procedure outlined in DLP-721 to verify the wiring of each shelf to the
MDF. If a wiring problem is found, correct the problem before proceeding.
3.
Verify Timing Connections
If timing connections have been made to the Total Access 3000/3010 Shelves,
perform the steps indicated below.
A.
Check for Timing Source Port Alarm
Visually check the output card on the timing source to ensure that no alarm
condition is associated with the output port connected to the Total Access
shelves.
B.
Check Waveform with Oscilloscope
This test step is optional but is recommended in cases where the clock wire
run is long or is routed past possible sources of interference. Use the
procedure in DLP-722 to verify that the input clock waveform meets
requirements.
4.
Verify Fan Operation
If Fan Units have been installed with the system, perform the steps indicated
below.
A.
Visually Verify Fan Operation
Visually verify that all of the fans are operating and that no obstructions are
present to impede free air flow through the shelves.
B.
Verify Fan Unit Alarm Input to SCU
Use the procedure outlined in DLP-723 to verify that the fan unit generates
the proper alarm when it fails.
5.
Verify Alarm Relay Output Connections
If a shelf’s alarm relays have been wired to external alarming equipment, use the
procedure in DLP-724 to verify that the alarm relay outputs are properly wired and
functioning.