MK Series Portable Chiller : Air-Cooled : HE INSTRUMENT
Page: 52
ADVANTAGE ENGINEERING, INC.
525 East Stop 18 Road Greenwood, Indiana 46142
317-887-0729 Fax: 317-881-1277
Service Department Fax: 317-885-8683
Email: service@AdvantageEngineering.com
11.
Clean motor shaft and
lubricate with a mild soap
solution.
12.
Install new stationary seal
member in pump casing
cavity (figure 5.5I). The
operator must be certain
the stationary seal member
is fully squared and seated
in cavity.
13.
Slide the rotating member
onto lubricated pump shaft
(figure 5.5J). The operator
must be certain not to
damage or tear rubber
bellows assembly.
14.
Place the spring onto the
rotating member.
15.
Align the impeller, spring
and rotating member
before reinstalling the
impeller (figure 5.5K). The
operator must be certain
the spring and rotating
member are aligned before
the impeller is fully tighten
and the impeller retaining
screw is reinstalled.
16.
Clean pump casing,
cavities, impeller and O-
ring before reassembly.
17.
Mate the motor and motor
adapter to the pump
casing. Reinstall the pump
casing bolts.
18.
Reconnect the motor
power cord and leads.
19.
Restore all cover panels as
were removed.
E.
When the pump seal replacement
procedure is complete, the
operator may restart the unit
according the
section 3
.
Stationary member
Figure 5.5I
Stationary member
Figure 5.5J
Seal members
Figure 5.5K
Seal components
Figure 5.5H
Summary of Contents for Maximum
Page 2: ......
Page 6: ...Page 6 THIS PAGE INTENTIONALLY BLANK ...
Page 44: ...Page 44 THIS PAGE INTENTIONALLY BLANK ...
Page 58: ...Page 58 THIS PAGE INTENTIONALLY BLANK ...
Page 79: ...END 2003 ADVANTAGE ENGINEERING INC RE 1 2 03 ...
Page 80: ......