6. UNPACKING AND INSTALLATION
This Section contains instructions for the site preparation, unpacking and the installation of the
SSPB Block Up-Converter.
6.1 INITIAL INSPECTION
Inspect the shipping container(s) for damage resulting from the shipment. If damaged,
immediately contact the carrier that delivered the equipment and submit a damage report.
Failure to do so may invalidate future claims.
6.2 UNPACKING
Carefully remove all of the items from the shipping container. Save all of the packing material
until completing successfully the visual inspection. For a single unit, verify that all of the items
listed on the packing list (see
Section 2
at page 9) have been received. If any of the items are
missing, contact Advantech Wireless immediately. Inspect all of the items for evidence of
damage resulting from the shipment. If damage seems evident, immediately contact the carrier
that delivered the equipment and file a claim. Failure to do so may invalidate future claims.
Check the SSPB units thoroughly for damaged or loose parts.
6.3 INSTALLATION
Installation of the SSPB Block Up-Converter requires the following phases:
Relay, Serial Interface and AC Power interconnecting cable construction
Environmental and adequate ventilation considerations
Mechanical, RF and electrical installation
TABLE 5
at page 20 lists all of the mounting connectors used by the SSPB unit and their
corresponding mating connectors.
Figure 3
at page 20 shows the location of the mounting
connectors.