3 Installation
24
Table3-4
Recommended cross-sectional area of wire (unit: mm
2
, environment temperature: 25
℃
)
type
30kVA
40kVA
Mode type
33 mode
31 mode
33 mode
31 mode
AC input live wire (U/V/W)
16*3
16*3
16*3
16*3
AC input neutral wire (N)
16*1
16*2
(parallel)
16*1
25*2 (parallel)
Bypass input live wire (U/V/W)
10*3
35*1
16*3
25*2 (parallel)
AC output live wire (U/V/W)
10*3
35*1
16*3
25*2 (parallel)
AC output neutral wire (N)
10*1
16*2
(parallel)
16*1
25*2 (parallel)
DC input (+/BATN/-)
16*3
16*3
25*3
25*3
Grounding wire (PE)
16*1
16*1
16*1
25*1
Table3-5
Contrast list between wires and wiring terminals
Wire cross-sectional area
(unit: mm
2
)
Wiring terminal type
Perforation
Straight cutting
4
RV3.5-6
/
6
RV5.5-6
/
10
RNBS8-6
E10-12
16
RNBS14-6
E16-12
25
RNBS22-6
E25-16
35
RNBS38-8
/
10kVA-20kVA UPS
The wiring terminals of 10kVA-20kVA UPS recommend type as shown in Table3-1. If users
have additional terminals required, please check dimensions to ensure proper selection
according to Table3-7.
Summary of Contents for IST9
Page 1: ...l un I Jet _________ __ AEC IST9 1 0 20 https www uni jet com catalog ibp on line ibp aec ist9...
Page 2: ...UPS IST9 10 20 kVA User Manual...
Page 3: ......
Page 9: ......
Page 52: ...3 Installation 43 Figure3 29 Diagram of 33 mode parallel system wiring of 10kVA 20kVA UPS...
Page 54: ...3 Installation 45 Figure3 31 Diagram of 33 mode parallel system wiring of 30kVA 40kVA UPS...
Page 82: ......