MFC Series Boilers Installation Manual
SECTION 7:
Assembly Of 4th Pass To Boiler
WARNING!
The Stainless Steel 4th Pass is heavy, so appropriate lifting devices, such as a fork lift (Figure
7-1), should be used. There are four lifting holes through which straps or hooks may be
attached for lifting. See Figure 7-1.
Attaching the Stainless Steel 4th Pass to the Boiler
1. Lift the Stainless Steel 4th Pass using an appropriate hoisting device anchored to the four
lifting holes provided in the Stainless Steel 4th Pass frame, as shown in Figure 7-1.
Figure 7-1: Lifting the Stainless Steel 4th Pass by Straps at the Four Lifting Holes
2. Guide the Stainless Steel 4th Pass into the correct position in relation to the boiler (see
Figure 7-2).
NOTE:
There is a “hooked” lower rim on the boiler that must fit onto the Stainless Steel 4th
Pass inner lower inner rim “lip” (see Figure 7-2) when mating the two together.
Figure 7-2: Positioning the Stainless Steel 4th Pass to the Boiler
FORK
LIFT
LIFTING
STRAPS
x4
LIFTING HOLES x4
CONNECTING
LIP
4
th
PASS
MOUNTING “LIP”
BOILER MOUNTING “HOOK”
Page
12
of
32
AERCO International, Inc.
•
100 Oritani Dr.
•
Blauvelt, NY 10913
OMM-0108_0A
12/15/2015
Ph.: 800-526-0288
GF-146-IN