WARNING

NEVER FORGET TO LOCK THE 

CASTOR WHEELS

DESCRIPTION:

The Advanced Guard Rail method:

The Advanced Guardrail (AGR) method is one of the two permitted ways of assembling a tower 

while safeguarding the Scaffolder from the risk of falling. 

An AGR tower uses prefabricated frames to provide structural rigidity and stability to the tower 

instead of using the horizontal and diagonal braces used for the same purpose in the traditional 

3T assembly method. 

As each new level is added onto a tower, the scaffolder first installs the AGR frames and tower 

frames from a safely guarded platform below. Once the AGR frames are in place, platforms for 

the next level are installed such that the two uppermost horizontal rungs on the AGR frames 

form the midrail and guardrail above the platform level. This process repeats until the tower 

reaches the required height.

Compliances:

The Affix 

MADW

 Mobile Tower has been tested and certified to 

EN1004-1:2020

 by 

TUV, India

.

The Affix 

MADW

 Series Mobile Tower are versatile and user-friendly aerial solution for all 

access needs. It gives a work platform for use by a maximum of two people, with weight evenly 

distributed across the platform. The tower can be easily erected and with highly customizable 

assembly it meets almost all the site constraints and provides safe and efficient working 

platform. The key safety feature is the smart locking claws provided for the horizontal and 

diagonal bracings. It allows an instant lock-up performed by single hand use, however, with the 

reverse unlocking plug, two hands are needed to unplug the bracing.

The information and instructions included in this manual are provided to help get the best 

possible service from your 

MADW

 Series Mobile Tower. This user guide provides you with step 

by step instructions to ensure your system is assembled easily and safely, using the 

AGR

 

(Advanced Guard Rail method.

02

Summary of Contents for MADW 1020-AGR

Page 1: ...Assembly Manual Double Width MADW AGR Series EN1004 1 Class 3 No CE 21 22 044...

Page 2: ...access tower manufactured in our ISO 9001 accredited facility This user guide provides you with step by step instructions to ensure your system is assembled easily and safely using the AGR Advanced Gu...

Page 3: ...required height Compliances The Affix MADW Mobile Tower has been tested and certified to EN1004 1 2020 by TUV India The Affix MADW Series Mobile Tower are versatile and user friendly aerial solution...

Page 4: ...ards e g electric cables No personnel or material to be on the platform whilst the tower is being moved Damaged components or components from other tower systems must never be used Stabilizers should...

Page 5: ...raises dust Gale force cannot even walk Raises loose papers leaves and small twigs move Strong breeze tree branches bend unable to use umbrella 3 4 5 6 Description Air Speed Action to be taken Ensure...

Page 6: ...triggers in the bracing hooks such that they are working properly Lock the castor by moving the brake lever fully down Sort the braces into horizontal and diagonal braces the diagonals are slightly l...

Page 7: ...ame and 2 Rung Span Frame Step 2 1 Step 2 1 Hook both the bottom 2 Horizontal Braces horizontally to the Span frame and the Ladder Frame s vertical pipes just above the 1st rung Step 2 2 Step 2 2 Lock...

Page 8: ...the 1st level Span frame at one end and the other end should be hooked to the 1st Rung of the 2nd level Ladder frame Step 4 2 Step 4 2 Hook the 2nd Diagonal Brace to the 1st Rung of the 2nd level Lad...

Page 9: ...e hooked to the 1st rung of the 2nd level frames Step 5 2 Repeat Step 5 1 for the opposite side but slide it towards the frame ladders to provide cover to the platform Step 6 Step 5 Clamp the 4 Stabil...

Page 10: ...frames Make sure the trapdoor is towards the ladder side 09 ASSEMBLY Step 7 1 Step 7 1 Insert both the 3rd level 4 Rung Span Frame and the 4 Rung Ladder Frame on the respective sides into the correspo...

Page 11: ...t Rung of the 3rd level Ladder frame Hook the 2nd Diagonal Brace to the 3rd Rung of the 2nd level Ladder frame at one end and the other end should be hooked to the 1st Rung of the 3rd level Span frame...

Page 12: ...ide Also hook the Fixed platform beside the Trapdoor platform on the same rungs Step 12 1 Step 12 1 Step 12 Step 12 2 Step 12 2 Clamp the 4 plastic toe board holders on all the 4 corners of the workin...

Page 13: ...ert the Side Toeboard and the End Toeboard in the respective toeboard slots as shown in the figure Clamping Instructions Always ensure the Spring Clips are in the lock position after inserting the upp...

Page 14: ...13 COMPONENTS FS20135 Span Frame FS10135 Span Frame BT200 250 ToeBoard Set FL10135 Ladder Frame FL20135 Ladder Frame CW150 200 JA500 Castor Wheel Adjustable Jack...

Page 15: ...PF200 250 Fixed Platform PT200 250 Trapdoor Platform ST200 300 450 600 Stabilizer BD200 250 BH200 250 Diagonal Brace Horizontal Brace 14 COMPONENTS AGR200 250 Advanced Guard Rail...

Page 16: ...Position the stabilizers so that the footpads are approximately equidistant from each other Adjust the stabilizers and reposition the clamps as required to make firm contact with the ground When in co...

Page 17: ...prepare the tower for use Check that the tower is vertical Reapply the castor brakes Check and adjust as necessary to ensure all castors and stabilizers are in firm contact with the ground Carefully m...

Page 18: ...der Frame Mini Span Frame Mini 4 0 4 0 2 0 0 0 1 1 1 1 1 1 4 0 4 2 2 0 0 0 1 1 1 1 2 2 0 0 0 4 4 2 4 4 0 0 2 1 1 2 2 1 1 0 4 4 2 4 4 0 0 2 1 1 3 3 0 0 0 4 4 2 6 4 0 0 3 1 1 3 3 1 1 0 4 4 2 6 0 4 0 3 1...

Page 19: ...EN1004 1 Certification by TUV India 18...

Page 20: ...affixscaffoldin https www linkedin com company affix scaffolding llc https www linkedin com company affix scaffolding llc https qrco de bcPyx6 To Check Assembly Video SCAN ME PO Box No 201633 Doha Qa...

Reviews: