Commissioning
22
Before starting up commissioning at site, please make sure below procedures
and requirements are fully meet.
• Mounting location is meet the requirements.
• All of the electrical wiring is firmly connected, including PV wiring, Grid wiring
and Earth wiring.
• The inverter setting has been finished accordingly to local standards or
regulations.
Commissioning Procedures
• Turn on the AC switch between inverter output and the public grid;
• Turn on the DC switch on the inverter;
• Turn on the PV switch of the system.
• Turn on the AC switch between the inverter and the public grid.
• Turn on the DC switch between PV panels and the inverter (if any).
• Turn on the DC switch on the inverter.
Inverter will enter into standby mode, and the LCD screen lights up and show
contents , and then complete the first setting of the inverter according to 5.3.1.
The LED will be lighted up after the inverter enter into running states.
Please check the following requirements before testing:
• Installation location is suitable according to Chapter 3.1.3.
• All electrical wires are connected tightly, including PV modules, AC side, Earth
Line.
• Inverters should be set according to the required local grid standard.
• More information please contact with Afore or distributors.
6. Commissioning
7. Start-up & Shut Down
7.1 Start-up