Performance Verification
15
Performance Verification
To ensure that the probe complies with the factory specifications,
perform the six tests in this section in the order listed. Connect the
required equipment listed in
Table 5
as shown in
Figure 6 on page
16
.
NOTE
Allow 30 minutes for warm up before starting the tests. While the test system is
warming up, clean the magnetic contacts on the probe’s jaw.
Construct a 10- turn coil with a diameter of about 4 inches (10 cm)
as shown in
Figure 5
. Use wire wrap or transformer wire and
attach stackable banana plugs to the coil for connection to the
instruments during testing.
Figure 5
10 Turn Coil
Table 5
Required Equipment for Performance Verification Tests
Description
Critical Specifications
Recommended
Model/Part Numbers
Digital Multimeter
(2 required)
AC/DC voltage and current
measurement accuracy better than
±0.1% of reading Input resistance in
AC/DC voltage mode
¡
1M
Ω
Agilent 34401A or Agilent 3458A
Signal Generator
DC to 100 kHz sine waves
Able to generate more than 10 mA in
the test coil (e.g. an inductive load).
Agilent 33120A or Fluke 5500A
Patch Cable Assembly
Banana plug connectors
Length
¤
36 in (91cm)
Pomona 1440-36-0
Adapter
BNC (m) to dual banana
Pomona 1296
Adapter
BNC (f) to dual banana
Pomona 1269
Banana Jack (2 required)
Stackable
Pomona 1325-0
Coil
10 turns (requires about 4 ft or 1.2 m
of transformer wire or wire wrap
wire.)
OK Industries R30B-0100(100 ft roll of
30AWG wire wrap wire)