Chapter 1 Performance Tests
Introduction
1-2
Assembly Level Service Guide
1
Introduction
This chapter provides procedures to test the electrical performance of the
Agilent 53147A, 53148A and 53149A. These procedures are based on the
specifications in Chapter 6, “Specifications.”
Two types of testing are provided:
•
Operational Verification
•
Complete Performance Tests
This chapter is organized as follows:
•
•
•
•
•
Performance Test Record
Operational Verification
Operational Verification is an abbreviated series of tests that you can
perform (instead of performing the Complete Performance Tests) to
provide a high degree of confidence that the instrument is operating
properly. Operational Verification is useful for incoming inspection,
routine maintenance, and after instrument repair.
Summary of Contents for 53147A
Page 6: ...Contents vi Assembly Level Service Guide ...
Page 13: ...1 Performance Tests Verifying Specifications ...
Page 55: ...2 Service ...
Page 88: ...Chapter 2 Service Troubleshooting the Instrument 2 34 Assembly Level Service Guide 2 ...
Page 89: ...3 Replacing Assemblies Disassembly and Reassembly ...
Page 104: ...Chapter 3 Replacing Assemblies Removing the Power Supply 3 16 Assembly Level Service Guide 3 ...
Page 105: ...4 Replaceable Parts ...
Page 116: ...Chapter 4 Replaceable Parts Parts Identification 4 12 Assembly Level Service Guide 4 ...
Page 117: ...5 Backdating ...
Page 119: ...6 Specifications ...
Page 125: ...A Rack Mounting the Instrument ...
Page 134: ...Index Index 4 Assembly Level Service Guide Index ...