Chapter 2.
Site Requirements
Sections in this chapter:
•
•
•
•
2.4 “Maximum Altitude” page 15
•
2.5 “Structural Strength of Floor” page 15
•
2.6 “Antivibration Bolt-Down Requirement” page 17
•
2.7 “Floor Vibration Requirements” page 17
•
2.8 “Magnetic Environment” page 18
•
2.9 “Radio-Frequency Environment” page 19
•
2.10 “Electrostatic Discharges” page 20
•
2.11 “Ambient Temperature and Humidity” page 20
•
•
2.13 “Helium and Nitrogen Refill Volumes and Intervals” page 21
Factors to consider when selecting the installation site include:
•
Accessibility to the delivery location
•
Site size and ceiling height
•
Floor rigidity and structural strength
•
Magnetic and radio frequency environment
•
Ambient temperature and humidity
•
Air ventilation
Each factor is covered in the sections in this chapter.