14
Air Breeze
Owner’s Manual
Ground
Chassis
Rod
Ground
Tower Ground
Battery
Black Lead
Turbine Negative
Red Lead
Disconnect
Turbine Positive
Fuse or
Breaker
Box
Switch
User Power
Stop
Center Junction
Turbine Ground
Green Lead
Earth Ground
Battery Bank
Tower
Amp
Meter
AIR BREEZE
Wind Turbine
Generator
Five - Air Breeze Wiring Options
The recommended way to connect the turbine to your battery bank
is to wire the turbine directly to its own set of battery posts. This will
allow the turbine to operate independently. The Air Breeze’s internal
regulator will monitor the battery and maintain the charge as neces-
sary.
Figs. 9 and 10
represent typical single turbine installations.
Fig. 10
includes an up-tower junction box for UL (Underwriters
Laboratory) compliance. Contact Southwest Windpower for more
information about this configuration.
TIP:
Wire turbine directly to
battery bank to its own set of
battery posts.
Fig. 9. Single Turbine Installation