Opening-closing of the dampers and control outputs: Turn on the system and generate demand in all the zones. Then,
switch off and on all the zones to verify the associated control outputs are correct.
-
Verify that the static pressure of the duct system complies with the air distribution network conditions where is
installed (check the Manufacturer’s Manual of the equipment if you need to modify this parameter).
Remember:
For security reasons, the last zones takes 4 minutes to close
.
FLOW REGULATION
Important:
Start adjusting the flow from the central dampers and finish off with damper 1.
FLOW ADJUSTMENT (REG)
1.
Turn on and generate demand in all zones to open all the dampers.
2.
Turn off the zone/damper to be adjusted.
3.
Adjust the maximum opening you want with the REG lever (I/II/III/IV).
4.
Turn on the zone and check the flow is correct.
MINIMUM AIR SETTING (A-M)
1.
Turn on and generate demand in all zones to open all the dampers.
2.
Adjust the minimum opening you want with the M-A lever (a/b/c/d).
3.
Turn on the zone and check the minimum air flow is correct.