11.
INSTALLATION
11.1. Preliminary operations
The machine is shipped completely assembled and packed on a pallet.
To load the machine from the pallet, resting it on the floor, use the special slide platform.
It is recommended not to push the machine from the pallet in the absence of a suitable
slide, but remove the batteries (if present) and unload it by hand, 4 people required
(approx. 30 kg per person max).
Before use perform the following operations:
1. Perform a preliminary inspection to identify any problems that might cause
malfunctioning or breakdowns.
Visually ensure there is no external damage, leaks and the wheels are not damaged.
3. Ensure the wiper is correctly adjusted.
4. Check that the drain hose, the cap, the hose from the wiper are installed properly, taking
care to insert the hose into a sharp bend with a suitable curve as shown in figure above.
5. Check battery conditions and if necessary recharge.
6. Ensure the brakes and steering wheel operate correctly.
Should any damage, fault or missing parts be detected, do not commission the machine
and contact your Dealer or directly Alberti International.
Summary of Contents for FKC 65 UB
Page 13: ...Manuale istruzioni FKC 65 UB 01 01 19 Rev 1 0 0 13 3 1 Dimensions...
Page 15: ...Manuale istruzioni FKC 65 UB 01 01 19 Rev 1 0 0 15 1 7 8 9 10 12 15 19 20 18 24...
Page 27: ...Manuale istruzioni FKC 65 UB 01 01 19 Rev 1 0 0 27...
Page 41: ...Manuale istruzioni FKC 65 UB 01 01 19 Rev 1 0 0 41...
Page 54: ...Manuale istruzioni FKC 65 UB 01 01 19 Rev 1 0 0 54...