Physical installation check
Overview
Purpose
A complete physical installation check should be done to ensure that all components are
complete and the cables are connected correctly.
Checks
The following units should be checked:
•
unit installation
•
cable connections.
The tests mentioned above are described in more detail in the following topics.
Contents
Physical and power installation exit checklist
AMC unit installation
Overview
This test checks the correct unit installation.
Checks
Check that:
•
there are no visible defects
•
the mechanical parts are secured
•
the optical couplings (or SFPs) are affixed to the optical interfaces
•
the E is up and running
Powering