E1 tributary ports distribution wiring test
Overview
This test verifies the following:
•
Checks the cabling with connections of all PDH ports with complementary wiring
according to the ODM
•
Verifies that the labeling on the DDF matches the correct port number.
Estimated duration
20 minutes
Test setup
The following figure illustrates a possible test setup:
ote:
For a long haul laser (L11, L12, L41 or L42) a 10 dB attenuator with applicable
connector is required in the loop.
Start condition
Ensure that the following start condition is fulfilled:
•
The procedure in section
“Preparation and test of the main unit” (p. 7-4)
must have
been performed and the test results are correct.
•
The ITM-CIT must be connected and logged-in to the E.
•
Test setup as shown in the figure above.
Figure 7-1 E1 tributary ports distribution wiring test
Stand-alone test procedures
E1 tributary ports distribution wiring test
...................................................................................................................................................................................................................................
...................................................................................................................................................................................................................................
365-313-103R8.0
Issue 2
July 2009
Alcatel-Lucent – Internal
Proprietary – Use pursuant to Company instruction
7-5