255-700-161
Checklist-3
PacketStar
®
PSAX 2300 Multiservice Media Gateway Installation Guide
, Issue 4
Installation Checklist
Checklists
4. Run and connect the frame ground cable (see
“Grounding the Chassis” on page 24 for details).
❒
5. Run and connect the unpowered (unfused) power
cabling between the power distribution/fuse panel and
product power supply connections (see “Connecting
the Facility Power Cables” on page 25 for details).
❒
6. Install and secure the common equipment modules:
power supply, CPU, Stratum 3–4, Alarm, etc., as
required (see “Installing the Common Equipment
Modules” on page 28 for details).
❒
*
You can take additional notes at the end of this section.
Checklist-2. Installing the Hardware (Continued)
Procedure
Your Notes/Comments
*
Checklist-3. Making the Common Equipment Connections
Procedure
Your Notes/Comments
*
1. Run and connect the console workstation cabling
(serial and/or Ethernet) for network management, sys-
tem control, and configuration (see “” on page 33 for
details).
❒
2. Run and connect the Stratum 3–4 clock cabling (see
“Connecting the External Facility Clock” on page 36
for details).
❒
3. Run and connect the system alarm, status, and control
cabling, if required. This step requires the Alarm
(20N79) module (see “Connecting the Alarm Module
(Model 20N79) to the CO” on page 36 for details).
❒
*
You can take additional notes at the end of this section.
Checklist-4. Applying Power to the System
Procedure
Your Notes/Comments
*
1. Turn the console workstation on.
❒