10  Details of mechanical mounting 

10.1  Aligning the mounting profiles 

10.1.1  Permissible alignment 
 

 

Fig. 3 

Permissible alignment of mounting profiles 

a, b

: Parallel profiles for mounting 

 

10.1.2  Not permissible alignment 

 

 

 
 
 

 
 

 

Fig. 4 

Not permissible alignment of mounting profiles 

 

a

: Profiles not parallel to each other 

b

: Profile neither parallel nor perpendicular to the module edges 

 

10.2  Clamp mounting for modules with standard frame 

10.2.1  Arranging the clamps 

 

Permissible clamp arrangement 

 

 

Fig. 5 

Permissible clamp arrangement 

a

: Symmetrical clamping on long sides 

b

: Symmetrical clamping on the short sides 

 

 

 

Not permissible clamp arrangement 

 

 

Fig. 6 

Not permissible clamp arrangement (1) 

a

: Missing clamps 

b

: Clamping on both short and long sides 

 

Fig. 7 

Not permissible clamp arrangement (2) 

c

: Protruding clamps 

d

: Opposing clamps have different distances to the module corners 

e

: Asymmetrical clamps on the short side 

 
 

10.2.2  Clamp dimensions 

Observe the following information for clamp lengths and depths. 
 

 

Clamp lengths and depths

 

 

Fig. 8 

Definition of clamp length and depth for framed modules 

a

: Clamp length 

b

: Clamp depth 

 

 

 

The required minimum length of a clamp (parallel to the frame 
side) is 30 mm. 

 

 

The required minimum depth of a clamp (perpendicular to the 
frame side) is 3 mm. 

 

 

aleo solar recommends a clamp depth of 5 mm. 

 

 

Depending on the ambient conditions (e.g. angle, suction load 

or tolerances of the substructure) a higher minimum area  per 
clamp may be required. 

 

 

Observe the instructions of the clamp manufacturer. 

 
 

10.2.3  Tightening torque for clamp mounting 

Tighten the screws on the clamp manually. If you use an automatic 

screwdriver,  then  set  a  suitable  maximum  tightening  torque.  You 
can  find  details  for  this  in  the  manufacturer’s  documentation  for 
the substructure. 

 

 

Summary of Contents for P23

Page 1: ...8 05 2021 en Page 1 of 20 INSTALLATION MANUAL For the aleo modules with standard frame 42mm X63 X61 X83 X81 with standard frame 35mm P23 with frame for the roof integration S83sol S81sol Please read...

Page 2: ...l BE Wenst u deze handleiding in het Nederlands te ontvangen neem dan contact op met de klantenservice van aleo solar zie hoofdstuk 2 2 2 Product support 2 1 Detailed information In addition to this R...

Page 3: ...afety precautions 8 8 3 Improper mounting 8 8 4 Intervals 8 8 5 Avoiding seals 9 8 6 Clearance under the modules 9 8 7 Shadowing 9 9 Electrical installation 10 9 1 Connectors 10 9 2 Laying the string...

Page 4: ..._________ WEIS NOTE indicates a potentially dangerous situation which can cause material damage if not avoided 4 2 Notes on modules The following symbol is attached to the modules If this symbol also...

Page 5: ...perience conditions that produce more current and or voltage than reported at standard test conditions 1 Accordingly the values of ISC and UOC marked on the modules should be multiplied by a factor of...

Page 6: ...les WARNING Damaged insulating back sheet Risk of electric shock and burns Avoid any contact with the back of the module with sharp or pointed objects Ensure that the back sheet remains undamaged 7 Pr...

Page 7: ...voltages possible even when the photovoltaic generator is disconnected if the generator is earthed Severe or fatal inju ries from electric shock If the circuit of your photovoltaic generator is earth...

Page 8: ...ield and re sults in loss of warranty rights Do not attach the modules by welding The temperatures cre ated in the process can cause delamination micro fissures and loss of yield and results in loss o...

Page 9: ...rtunity to affect the shadowing then take another site into consideration or only plan with the non shadowed parts of your site when you configure your photovoltaic generator 8 7 2 Effects of shadowin...

Page 10: ...4 connectors are referred to as MC4 in the data sheet 9 2 Laying the string cables CAUTION Brittle fractures in junction boxes due to contact with unsuitable connection cables Risk of fire Only use co...

Page 11: ...lectric shock Leave the planning and installation of the external and if re quired internal lightning protection to be always carried out by qualified technicians It is essential to integrate an arres...

Page 12: ...both short and long sides Fig 7 Not permissible clamp arrangement 2 c Protruding clamps d Opposing clamps have different distances to the module corners e Asymmetrical clamps on the short side 10 2 2...

Page 13: ...s A load can be a pressure load as well as a suction load Loads from snow and wind are grouped into several levels which need to be considered wherever the module is installed Higher load levels make...

Page 14: ...test load Clamping long side 0 mm 458 mm Load level I 2400 Pa 2400 Pa 120 mm 458 mm Load level II 3900 Pa 2400 Pa 220 mm 458 mm Load level III 5400 Pa 2400 Pa 220 mm 300 mm Load level IV 8000 Pa 5400...

Page 15: ...0 mm 293 mm Load level I 2400 Pa 2400 Pa 120 mm 293 mm Load level II 3900 Pa 2400 Pa 180 mm 293 mm Load level III 5400 Pa 2400 Pa 180 mm 220 mm Load level IV 8000 Pa 5400 Pa Clamping short side 0 mm...

Page 16: ...t load Permissible suction test load Clamping long side 0 mm 458 mm Load level I 1400 Pa 1400 Pa 220 mm 458 mm Load level II 3900 Pa 2400 Pa 220 mm 300 mm Load level III 5400 Pa 2400 Pa Clamping short...

Page 17: ...om trees or neighbouring houses 11 1 2 Inspection of the documentation and drawings check the module string plan 7 check the inverter s status reports determine and archive the annual output create an...

Page 18: ...of deposits is avoided 12 This prevents mechanical tension in the glass and ensures the module a longer service life For stubborn patches of dirt use the following to help Isopropanol aleo solar recom...

Page 19: ...precautions and chap 6 2 1 Electrical safety precautions 11 5 2 System parts For repairing other system parts e g substructure connection boxes contract authorised technicians to do the work or contac...

Page 20: ...Stra e 1 17291 Prenzlau Germany info aleo solar com Installation manual Ver 4 8 05 2021 en Page 20 of 20 Aleo solar GmbH Marius Eriksen Stra e 1 17291 Prenzlau Germany Contact 49 0 3984 8328 0 info al...

Reviews: