1. Use the lifting straps provided with the paving machine. The straps are
rated at 28,000 lbs. when used in the basket configuration.
2. Attach ropes to each end of the machine to help preventing the machine
from swinging while being lifted.
3. The center cable length should be carefully adjusted.
4. Keep all strap or chain lift angles at 45° or greater from horizontal.
5. To balanced machine, position the paving carriage opposite the power unit
end. Lift the machine 10 to 12 inches off of the ground Move the paving
carriage until the machine is balanced. If the carriage travel chain. Lock the
carriage down to prevent the carriage from moving while lifting preventing
a unleveled load.
CAUTION! Do not allow the weight of the machine to rest on the
carriage or the paving rollers. Damage to the carriage or the
paving rollers could result.
36’ to 48’ Machine (Appx Weight 6,500 to 10,500 Lbs.)
84’ to 108’ Machine (Appx Weight 10,000 to 13,500 Lbs.)
WARNING! Use extreme caution when lifting the
Concrete paving machine. All lifting devices must
meet or exceed the required capacity to lift the
weight of the machine. Check all slings, chains,
clevises, and cable clamps for strength and for
structural damage. If any are damaged in anyway
replace, before lifting machine
WARNING! Before lifting the machine make sure
that the machine jacks are locked in place! To pre-
vent the jacks from swing out and making the paver
in balanced and causing personal injury.
WARNING! Make Sure to keep all personnel back
and away from the machine while it is being lifted.
SECTION 2
OPERATIONS
050362
Page 28
2.3 - Lifting the Machine
Summary of Contents for BDF4836B
Page 5: ...050362 Page 5 Table of Contents continued ...
Page 14: ...050362 Page 14 Notes ...
Page 15: ...SECTION 1 SAFETY 050362 Page 15 SECTION 1 SAFETY ...
Page 21: ...SECTION 1 SAFETY 050362 Page 21 PAGE LEFT BLANK INTENTIONALLY ...
Page 22: ...Notes SECTION 1 SAFETY 050362 Page 22 ...
Page 23: ...SECTION 2 OPERATIONS 050362 Page 23 SECTION 2 OPERATIONS ...
Page 40: ...Power Crown Lever Nut A SECTION 2 OPERATIONS 050362 Page 40 2 6 Power Crown Option ...
Page 46: ...Skew Clamp Skew Cylinder SECTION 2 OPERATIONS 050362 Page 46 2 7 Paving Operations continued ...
Page 49: ...SECTION 2 OPERATIONS 050362 Page 49 PAGE LEFT BLANK INTENTIONALLY ...
Page 50: ...SECTION 2 OPERATIONS 050362 Page 50 Notes ...
Page 51: ...SECTION 3 SERVICE 050362 Page 51 SECTION 3 SERVICE ...