Other Unit Adjustments

Primary Limit

The primary limit is located on the heating compartment 

vestibule  panel. This  limit  is  factory  set  and  requires  no 

adjustment.

Flame Rollout Switches (Two)

These manually reset switches are located on the front of 

the burner box. These limits are factory set and require no 

adjustment.

Pressure Switch

The pressure switch is located in the heating compartment 

on the cold end header box. This switch checks for proper 

combustion air inducer operation before allowing ignition 

trial. The switch is factory set and must not be adjusted.

Temperature Rise

After the furnace has been started and supply and return 

air  temperatures  have  been  allowed  to  stabilize,  check 

the  temperature  rise.  If  necessary,  adjust  the  blower 

speed  to  maintain  the  temperature  rise  within  the  range 

shown on the unit nameplate. See Table 15 for allowable 

heating  speeds.  Increase  the  blower  speed  to  decrease 

the temperature. Decrease the blower speed to increase 

the temperature rise. Failure to adjust the temperature rise 

may cause erratic limit operation.

Fan Control

The fan ON time of 30 seconds is not adjustable. The fan 

OFF delay (amount of time that the blower operates after 

the  heat  demand  has  been  satisfied)  may  be  adjusted 

by  changing  the  jumper  position  across  the  five  pins  on 

the integrated control. The unit is shipped with a factory 

heat fan OFF setting of 120 seconds. The fan OFF delay 

affects  comfort  and  is  adjustable  to  satisfy  individual 

applications. Adjust the fan OFF delay to achieve a supply 

air  temperature  between  90°  and  110°  F  at  the  moment 

that the blower is de-energized. Longer OFF delay settings 

provide  lower  return  air  temperatures;  shorter  settings 

provide higher return air temperatures. See Figure 62.

Thermostat Heat Anticipation

Set the heat anticipator setting (if adjustable) according to 

the amp draw listed on the wiring diagram that is attached 

to the unit.

Electrical

1.  Check all wiring for loose connections.
2.  Check  for  the  correct  voltage  at  the  furnace  (with 

furnace operating). Correct voltage is 120 VAC ± 10%. 

3.  Check amp–draw on the blower motor with the blower 

compartment access panel in place.

Motor Nameplate____________Actual____________

Figure 62. 

Heat Fan-OFF Time in Seconds

Blower Speeds

Follow the steps below to change the blower speeds.

1.  Turn off electrical power to furnace.

2.  Remove blower compartment access panel.
3.  Disconnect existing speed tap at control board speed 

terminal.

NOTE: 

Termination of any unused motor leads must 

be insulated.

4. 

Place unused blower speed tap on integrated control 

“PARK” terminal or insulate.

5.  Refer to blower speed selection chart on unit wiring 

diagram  for  desired  heating  or  cooling  speed.  See 

Blower performance data beginning on the next page. 

See Table 15 for allowable heating speeds.

6. 

Connect selected speed tap at control board speed 

terminal.

7.  Re-secure blower access panel.
8.  Turn on electrical power to furnace.
9.  Recheck temperature rise.

Electronic Ignition

The integrated control has an added feature of an internal 

Watchguard control. The feature serves as an automatic 

reset  device  for  integrated  control  lockout  caused  by 

ignition failure. This type of lockout is usually due to low 

gas line pressure. After one hour of continuous thermostat 

demand for heat, the Watchguard will break and remake 

thermostat demand to the furnace and automatically reset 

the integrated control to begin the ignition sequence.

Exhaust and Air Intake Pipe

1.  Check exhaust and air intake connections for tightness 

and to make sure there is no blockage.

2.  Is  pressure  switch  closed?  Obstructed  exhaust  pipe 

will cause unit to shut off at pressure switch. Check 

termination for blockages.

3. 

Obstructed pipe or termination may cause rollout 

switches to open. Reset manual flame rollout switches 

on burner box assembly if necessary.

Summary of Contents for 045-B12

Page 1: ...nal injury or loss of life Installation and service must be performed by a licensed professional installer or equivalent service agency or the gas supplier WARNING As with any mechanical equipment per...

Page 2: ...507868 02 Page 2 of 48 Issue 2128 Unit Dimensions Capacity A B C in mm in mm in mm 045 B12 070 B12 17 1 2 446 16 3 8 416 16 406 090 C16 21 533 19 7 8 504 19 1 2 495...

Page 3: ...Heating Compartment Access Panel Blower Access Panel Cold End Header Box Control Box includes integrated control transformer and door switch Blower Assembly Bag Assemblies Cabinet Blower Deck Heat Exc...

Page 4: ...aded street elbow Check equipment for shipping damage If you find any damage immediately contact the last carrier Please refer to specification sheets for available accessories Safety Information DANG...

Page 5: ...must be equipped to prevent operation of either the heating or the cooling unit unless it is in the full HEAT or COOL setting When installed this furnace must be electrically grounded according to lo...

Page 6: ...afts might blow directly into it This could cause improper combustion and unsafe operation When the furnace is installed in a non direct vent applications do not block the furnace combustion air openi...

Page 7: ...ombustion and ventilation depend largely on whether the furnace is installed in an unconfined or a confined space Unconfined Space An unconfined space is an area such as a basement or large equipment...

Page 8: ...n of rectangular air ducts shall be no less than 3 inches 75 mm In calculating free area the blocking effect of louvers grilles or screens must be considered If the design and free area of protective...

Page 9: ...ned Space all Air from Outside Shipping Bolt Removal Units with 1 2 hp and 3 4 hp blower motors are equipped with three flexible legs and one rigid leg The rigid leg is equipped with a shipping bolt a...

Page 10: ...o not drag the unit across the floor in the downflow position Floor and furnace flange damage will result Refer to Figure 14 for clearances in downflow applications Improper installation of the furnac...

Page 11: ...2 After opening is cut set the combustible flooring base into opening 3 Check fiberglass strips on the combustible flooring base to make sure they are properly glued and positioned 4 Lower supply air...

Page 12: ...external static pressure which exceeds 0 5 inches w c Operation at these conditions may result in improper limit operation Supply Air Plenum If the furnace is installed without a cooling coil a remova...

Page 13: ...ces of ignition Do not use excessive amounts of solvent cement when making joints Good ventilation should be maintained to reduce fire hazard and to minimize breathing of solvent vapors Avoid contact...

Page 14: ...Termination kits 44W92 and 44W93 are approved for use in Canadian installations to meet CSAB149 The 44W92 Concentric kit is provided with a 1 1 2 accelerator which must be installed on the exhaust ou...

Page 15: ...condition 3 Close all building doors and windows and all doors between the space in which the appliances remaining connected to the common venting system are located and other spaces of the building T...

Page 16: ...utdoors and flue gases are discharged outdoors Intake and exhaust pipe sizing Size pipe according to Table 6 and Table 7A through Table 7B Table 6 lists the minimum vent pipe lengths permitted Table 7...

Page 17: ...13 97 97 78 8 26 11 60 45 n a 92 92 73 9 21 n a 55 40 87 87 68 10 16 50 35 82 82 63 Concentric Termination Elevation 0 10 000 ft Number of 90 Elbows Used 1 1 2 Pipe 2 Pipe 2 1 2 Pipe 3 Pipe Model Mode...

Page 18: ...48 10 6 40 55 62 62 43 NOTE Additional vent pipe and elbows used to terminate the vent pipe outside the structure must be included in the total vent length calculation Figure 23 Typical Exhaust Pipe C...

Page 19: ...must be considered Guidelines listed in Combustion Dilution and Ventilation Air section must be followed Follow the next two steps when installing the unit in Direct Vent applications where combustion...

Page 20: ...r to Outside Roof Terminated Exhaust Pipe Furnace Ventilation Louvers Crawl Space Intake Debris Screen Provided Inlet Air Minimum 12 in 305mm above Crawl Space Floor Coupling or 3 in to 2 in Transitio...

Page 21: ...in Unconditioned Space for Winter Design Temperatures Single Stage High Efficiency Furnace Winter Design Temperatures1 F C Vent Pipe Diameter Unit Input Size 045 070 090 32 to 21 0 to 6 PVC 2 PP PVC 2...

Page 22: ...arance under veranda porch deck or balcony 12 Equal to or greater than soffit depth 3 feet 9m 12 3 feet 9m within a height 15 feet 4 5m above the meter regulator assembly 3 feet 9m 6 inches 152mm for...

Page 23: ...s 152mm for appliances 10 000 pliances 10 000 Btuh 3kw and 50 000 pliances 50 000 Btuh 15kw 6 inches 152mm for appliances 10 000 Btuh 3kw 12 inches 305mm for appliances 10 000 Btuh 3kw and 100 000 Btu...

Page 24: ...tion is 3 76 mm on roof terminations and 6 152 mm on side wall terminations 3 On roof terminations the intake piping should terminate straight down using two 90 elbows see Figure 31 4 Exhaust piping m...

Page 25: ...accelerator provided on 71M80 44W92 kits for 045 and 070 models 12 305mm INTAKE AIR EXHAUST VENT Figure 36 Direct Vent Concentric Wall Termination 71M80 69M29 or 60L46 US 44W92 or 44W93 Canada 12 305m...

Page 26: ...tee should be connected to the 2 or 3 PVC flue pipe as shown in the illustration Do not use an accelerator in applications that include an exhaust termination tee The accelerator is not required 2 As...

Page 27: ...TION SIZE PER EXHAUST PIPE TERMINATION SIZE REDUCTION TABLE Figure 41 Non Direct Vent Field Supplied Wall Termination SIZE TERMINATION PER EXHAUST PIPE TERMINATION SIZE REDUCTION TABLE FIELD PROVIDED...

Page 28: ...ermination Drain Trap assembled Figure 44 Kit 51W18 USA 15Z70 Canada Parts Identification and Assembly Exhaust from Furnace To Termination Exhaust from Furnace To Termination Kit 51W18 is shown Figure...

Page 29: ...be 1 1 4 ODx1 ID and should be attached to the drain on the trap using a hose clamp Figure 47 Condensate Trap and Plug Locations Trap same on right side Plug same on left side 1 1 2 in 5 Figure 49 sho...

Page 30: ...507868 02 Page 30 of 48 Issue 2128 Figure 49 Evaporator Coil Using a Separate Drain Figure 50 Evaporator Coil Using a Common Drain Figure 51 Condensate Trap with Optional Overflow Switch...

Page 31: ...507868 02 Page 31 of 48 Issue 2128 Figure 52 Trap Drain Assembly Using 1 2 PVC or 3 4 PVC...

Page 32: ...ed on the gas valve to facilitate test gauge connection See Figure 53 6 In some localities codes may require installation of a manual main shut off valve and union furnished by installer external to t...

Page 33: ...4 118 3 34 110 3 11 103 2 92 1 25 4 1 049 26 645 680 19 25 465 13 17 375 10 62 320 9 06 285 8 07 260 7 36 240 6 80 220 6 23 205 5 80 195 5 52 1 1 4 31 75 1 380 35 052 1400 39 64 950 26 90 770 21 80 66...

Page 34: ...long enough to facilitate future removal of blower for service Complete the wiring connections to the equipment Use the provided unit wiring diagram and the field wiring diagram shown in Figure 58 Use...

Page 35: ...run on the heating speed 3 When there is a cooling demand the indoor blower will run on the cooling speed Generator Use Voltage Requirements The following requirements must be kept in mind when speci...

Page 36: ...507868 02 Page 36 of 48 Issue 2128 Figure 59 Typical Wiring Diagram...

Page 37: ...next to the floor because some gas is heavier than air and will settle on the floor The gas valve on the unit is equipped with a gas control switch lever Use only your hand to move switch Never use to...

Page 38: ...low the gas supplier s instructions If you do not smell gas go to next step 8 Move gas valve switch to ON See Figure 61 9 Replace the heating compartment access panel 10 Turn on all electrical power t...

Page 39: ...t unit and allow 5 minutes for unit to reach steady state 3 While waiting for the unit to stabilize observe the flame Flame should be stable and should not lift from burner Natural gas should burn blu...

Page 40: ...Orifice Kit All 11K50 73W80 51W01 11K45 Conversion requires installation of a gas valve regulator spring which is provided with the gas conversion Kit LP Kits include low line pressure switch Pressure...

Page 41: ...2 Visually inspect the venting system for proper size and horizontal pitch Determine there is no blockage or restriction leakage corrosion or other deficiencies which could cause an unsafe condition 3...

Page 42: ...ticipator setting if adjustable according to the amp draw listed on the wiring diagram that is attached to the unit Electrical 1 Check all wiring for loose connections 2 Check for the correct voltage...

Page 43: ...351 1265 276 1140 202 860 109 700 73 0 20 1345 360 1240 285 1090 208 810 119 645 79 0 30 1325 371 1215 291 1060 218 770 124 590 84 0 40 1295 380 1175 302 1025 228 710 132 530 91 0 50 1260 392 1135 31...

Page 44: ...ure proper furnace operation Table 3 lists recommended filter sizes Exhaust and Air Intake Pipes Check the exhaust and air intake pipes and all connections for tightness and to make sure there is no b...

Page 45: ...abinet Remove two screws from blower rail which secure bottom heat exchanger flange Remove heat exchanger from furnace cabinet 17 Back wash heat exchanger with soapy water solution or steam If steam i...

Page 46: ...nt will be displayed first LED off for 3 sec then next error code is displayed etc To clear error codes depress and hold button longer than 5 seconds Cleaning the Burner Assembly 1 Turn off electrical...

Page 47: ...Problems detected during the inspection may make it necessary to temporarily shut down the furnace until the items can be repaired or replaced Instruct the homeowners to pay attention to their furnac...

Page 48: ...height of eight 8 feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment The sign shall read in print size no less than...