Chapter 6: Powering On the Switch
86
5. Connect the power cords to an appropriate AC power source. Refer to
Figure 38. Connecting the Power Cords to an AC Power Source
Note
The illustration shows a North American power cord. Your power
cords may be different.
6. Repeat steps 1 to 4 to connect the second AC power cord.
7. Do one of the following:
To monitor the switch as it initializes the management software, go
to “Monitoring the Initialization Processes” on page 87.
Wait two minutes for the switch to initialize its management
software and then go to Chapter 7, “Configuring the Switch for
Summary of Contents for AlliedWare Plus AT-x530 Series