AT-SBx908 GEN2 Installation Guide for Virtual Chassis Stacking
139
Figure 94. Switch Initialization Messages (Continued)
After the switch has initialized its management software, go to Chapter 6,
“Configuring Switches for Stacking” on page 141.
Assigning Active Workload to HA processes:
hsl, authd, epsrd, imi, imiproxyd, irdpd, lacpd
lldpd, loopprotd, mstpd, nsm, ospfd, ripd, rmond
sflowd, vrrpd
Received event network.activated
Loading default configuration
....
done!
Received event network.configured
awplus login: