Installing Direct Attach Cables
Table 10 on page 39 lists the direct attach cables for the base ports and
XEM2 Line Cards. They offer an economical way to add 10Gbps, 40Gbps,
or 100Gbps connections over short distances. To install direct attach
cables, perform the following procedure:
1. Select a port for the direct attach cable.
2. If the selected port has a dust cover, remove the cover.
3. Remove the transceiver from its shipping container and store the
packaging material in a safe location.
4. Orient the transceiver and slide it into the port until it clicks into place.
The correct orientation depends on the cable:
Figure 133 shows the orientations for SP10TW direct attach cables
installed in base ports 1 to 24 and XEM2-8XSTm and XEM2-12XS
Cards.
Figure 133. Installing SP10TW Direct Attach Cables
Figure 134 on page 236 shows the orientations for QSFPCU
Cables installed in base ports 25 to 37.
Release Tab
Summary of Contents for x950 Series
Page 12: ...Figures 12 ...
Page 18: ...Preface 18 ...
Page 50: ...Chapter 1 Overview 50 ...
Page 70: ...Chapter 2 XEM2 Ethernet Line Cards 70 ...
Page 134: ...Chapter 5 Installing Power Supplies and Optional XEM2 Line Card 134 ...
Page 146: ...Chapter 7 Installing the Switch in an Equipment Rack 146 ...
Page 162: ...Chapter 8 Installing the Switch on a Wall 162 ...
Page 224: ...Chapter 12 Powering On and Verifying the Stack 224 ...
Page 256: ...Chapter 14 Replacing Modules 256 ...