9. Remove screws from both sides, top and bottom of
vestibule panel.
10. Remove heat exchanger. It may be necessary to
spread cabinet side to allow more room. If so, remove
five screws from the left side or right side of cabinet.
See Figure ??.
11. Back wash using steam. Begin from the burner opening
on each clam. Steam must not exceed 275°F.
12. To dean burners, run a vacuum deaner with a soft brush
attachment over the face of burners. Visually inspect
inside the burners and crossovers for any blockage
caused by foreign matter. Remove any blockage.
Figure ?? shows burner detail.
13. To dean the combustion air inducer visually inspect
and using a wire brush clean where necessary. Use
cornpressed air to clean off debris and any rust.
14. Reinstall heat exchanger in vestibule. (Replace the five
screws in the cabinet from step 10 if removed).
15.
NOX units only
- replace NOX inserts.
16. Reinstall collector box and combustion air assembly.
Reinstall all screws to the collector box and combustion
air inducer. Failure to replace all screws may cause
leaks. Inspect gaskets for any damage and replace if
necessary.
17. Reinstall burner box, manifold assembly and burner box
cover.
18. Reconnect all wires.
19. Reconnect top cap and vent pipe to combustion air
inducer outlet.
20. Reconnect gas supply piping.
21. Turn on power and gas supply to unit.
22. Set thermostat and check for proper operation.
23. Check all piping connections, factory and field, for gas
leaks. Use a leak detecting solution or other preferred
means.
Some soaps used for leak detection are corrosive to
certain metals. Carefully rinse piping thoroughly after
leak test has been completed. Do not use matches,
candles, flame or other sources of ignition to check for
gas leaks.
CAUTION
24. If a leak is detected, shut gas and electricity off and
repair leak.
25. Repeat steps 24 and 26 until no leaks are detected.
26. Replace access panel.
Figure 39
NOX Inserts
Figure 40
Remove 5 Screws if Necessary
(either side of cabinet)
Summary of Contents for 80G2UH-V
Page 29: ...507335 01 Page 29 of 44 Issue 1624 ADJUSTING AIRFLOW Table 11 ...
Page 41: ...507335 01 Page 41 of 44 Issue 1624 Wiring Diagram Figure 41 ...
Page 42: ...507335 01 Page 42 of 44 Issue 1624 Typical Field Wiring Diagram Figure 42 ...
Page 43: ...507335 01 Page 43 of 44 Issue 1624 Start Up Performance Check List UNIT SET UP ...
Page 44: ...507335 01 Page 44 of 44 Issue 1624 UNIT OPERATION ...