Page 2 of 16
506941-01
Issue 1148
INSTALLATION
These units are certifi ed by E.T.L. Testing Laboratories, Inc.:
•
For use as a forced air furnace with cooling unit.
•
For outdoor installation only.
•
For installation on combustible material.
•
For use with natural gas or LP/propane gas.
(Conversion kit required for propane gas application.)
These units are not suitable for use with conventional
venting systems.
T
hese instructions must be kept with this unit in a
conspicuous place.
These units are single package air conditioners with gas
heat designed for outdoor installation on a rooftop or a slab.
The units are completely assembled. All piping, refrigerant
charge, and electrical wiring are factory installed and tested.
The units require only electric power, gas piping, condensate
drain, and duct connections, plus installation of the vent
cover at the point of installation.
If components are to be added to a unit to meet local codes,
they are to be installed at the dealer’s and/or customer’s
expense.
The size of unit for the proposed installation should be based
on heat loss/heat gain calculation made according to the
methods of Air Conditioning Contractors of America (ACCA).
See Table 1 for fi lter information and application limitations.
These installation instructions are intended as a general
guide only, for use by an experienced, qualified
contractor.
Exercise care when moving the unit. Do not remove any
packaging until the unit is near the place of installation.
Spreaders whose length exceed the largest dimension
across the unit
must be used across the top of the unit.
Units may also be moved or lifted with a forklift while still in
the factory supplied packaging.
The lengths of the forks
of the forklift must be a minimum of 42”.
Inspection
As soon as the unit is received, it should be inspected for
possible damage during transit. If damage is evident, the
extent of the damage should be noted on the carrier’s freight
bill. A separate request for inspection by the carrier’s agent
should be made in writing.
Location
Use the following guidelines to select a suitable location
for these units.
1. Unit is designed for outdoor installation only. Unit must
be installed so all electrical components are protected
from water.
2. Condenser coils must have an unlimited supply of air.
3. For ground level installation, use a level prefabricated
pad or use a level concrete slab. Do not tie the slab to
the building foundation.
4. Maintain level within a tolerance of 1/4” maximum across
the entire length or width of the unit.
5. Do not locate the unit where the combustion air supply
will be exposed to any of the following substances:
•
Permanent wave solutions
•
Chlorinated waxes and cleaners
•
Chlorine-based swimming pool chemicals
•
Water softening chemicals
•
Deicing salts or chemicals
• Carbon
tetrachloride
• Halogen-type
refrigerants
•
Cleaning solvents (such as perchloroethylene)
•
Printing inks, paint removers, varnishes, etc.
•
Cements and glues
•
Antistatic fabric softeners for clothes dryers
•
Masonry acid washing materials
•
Chlorinated laundry products
• Hydrochloric
acid
In the State of Massachusetts:
This product must be installed by a licensed Plumber
or Gas Fitter. When fl exible connectors are used, the
maximum length shall not exceed 36”. When lever-type
gas shutoffs are used, they shall be T-handle type.
WARNING
Before lifting a unit, make sure that the weight is
distributed equally on the cables so that it will lift evenly.
CAUTION