12
Gland & Conduit Installation
1. Select appropriate glands to replace the plugs on the underside of the SolShare. (See Appendix for details)
2. Replace plugs with input gland and required number of output glands.
- The number of output glands required will depend on the number of units connected to the SolShare.
- One gland for every 2 units is recommended. However, fewer glands may be used if cable gauge permits.
3. Run input conduit from inverter to SolShare input (via Solar Main Switch)
4. Run output conduits from out glands to Unit Solar Circuit Breakers
TO METER
PANEL
FROM
INVERTER
PRE-EXISTING
EARTH CONNECTIONS
TO ENCLOSURE
Important:
The Unit Solar Circuit Breakers can be mounted on the meter panel or in a separate enclosure adjacent
to meter panel (as pictured on page 8)
Important:
- No wiring loops of excess conductor length are allowed to be made. Field wiring of all circuits must maintain
1/4” separation from all other circuits
- All electrical connections including sensor circuits, made between the Allume Energy SolShare 100 and
an electrical distribution panel shall be run through conduit or another type of NEC compliant raceway