2.1 Building
This gateway has 3 LEDs at the front:
1.
Signalling of radio connection with air handling unit
2.
Signalling of establishing connection with the ALNOR server (registration of the gate
in the ALNOR database)
3.
Power supply indication
The gateway has 2 ports:
RJ45 - fireplace
USB typu B - power
NOTE:
Do not use the RESET button. Pressing it will erase the access data to the ALNOR server.
Such gateway will need to be re-programmed at our headquarters.
3. Installation
3.1 The contents of the box
1. Communication module; 2. Power adapter; 3. USB cable; 4. Ethernet cable; 5. Manual
3.2 Connection steps
1. Connect the HRQ-PremAIR-GATE with the Ethernet cable to the router.
2. Connect the power adapter with the USB cable to the device and power supply.
3. After a few seconds the power LED (3) will light up.
!