2.
Installation
This Manual introduces the basic steps how to install and operate AlphaESS battery
system: SMILE-BAT-G3-10.1P series.
SMILE-BAT-G3-10.1P is a sealed component with no access to battery terminals or cell
components within module.
SMILE-BAT-G3-10.1P contains a Bi-pole DC isolator, which conforms to IEC 60947. It has
been operated in all live conductors
NOTE: please pay attention for unpacking the battery, the worst case
is that some components could be damaged.
Installation Site and Environment
General
The externals enclosure’s material is 430 steel (SUS 430). The material thickness is 1.5
mm.
The SMILE-BAT-G3-10.1P can be installed in an outdoor or an indoor location.
In SN
□□□
-YYMMXXXX.
Where battery systems are installed within a room, shall be located so that access to the
battery is not obstructed by the structure of the building, fixtures and fittings within the room.
SMILE-BAT-G3-10.1P adopts natural ventilation. The location should be clean, dry and
adequately ventilated. The room’s entry doors and panels shall open in the direction of
egress and allow unobstructed access to the battery for installation and maintenance
purposes.
The following location are
not allowed
for installation:
habitable rooms;
in ceiling spaces;
wall cavities;
on roofs not specifically deemed suitable;
areas of access/egress;
under stairways;
under access walkways;
sites where the freezing point is reached, like garages, carports or other places;
sites with humidity and condensation over 85%;
sites which are salty and where humid air can penetrate;
earthquake areas –additional security measures are required here;
sites that are higher than 3000 meters above the sea level;