EMS Introduction and Set up
Step 1:
Click Enable to set yes.
Step 2:
Set the priority of the load,
L1
>
L2
>
L3
B.
If external device will dispatch the system, please set as following steps:
Step 1:
Please go to the function menu, choose
“ModBus” and press enter.
Step 2:
Please set Modbus enable as yes.
C.
If you use cascading function please set as following steps:
Step 1:
Please go to the function menu, choose
“Parallel” and press enter.
Step 2:
Please choose “Select” as “Yes” and
press enter.
Step 3:
Please choose “Phase” as L1 (master)
and press enter.
Step 4:
Please choose “Mode” as “Parallel
mode” and press enter.
Step 5:
please repeat Step 1 to 4 to set the other device as L2 (slave) L3 (slave).