4.
Installation
Installation Precautions
The following sites are not allowed for installation:
- Sites which are salty and where humid air can penetrate.
- Flooded areas.
- Earthquake areas
–additional security measures are required here.
- Sites that are higher than 3000 meters above the sea level.
- Sites with explosive or potentially explosive atmosphere.
- Sites with extreme changes of ambient temperature.
- Sites with highly flammable materials or gases.
Packing List
Table 11 Packing List
M48112-S
4 x M6*16
4 x M6 Gouding Serrated
Washer
1 x
130 mm Power Cable
black-red, BAT-BAT
1 x Communication cable
280 mm, BAT-BAT
Cabinet
1 x 130 mm
Power Cable
black-black, BAT-HV
1 x 2120 mm Power Cable
red-red, BAT-HV
1 x
2300 mm Power Cable
black-red, BAT-BAT
1 x Communication cable
2200 mm, BAT-HV900112