Installation
Filling with SF
6
gas
M32--001EN06
7/10
02--2011
© ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be
relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is
strictly prohibited.
GRID
Checking pressure
, continued
Decision table
The table below gives the process depending the pressure measured :
14
16
If the pressure measured is ...
Action
correct
End of control
too high
Adjust the pressure by means of valve
(16) on the gauge (14) to reach the re-
quired corrected pressure.
too low
Top--up with SF
6
gas
If the pressure
adjustment
is ...
Action
≤
0,05 MPa
End of control
>
0,05 MPa
Proceed to a
new inspection
after a stabiliza-
tion period of
2--3 hours.
End of control
The table below gives the end steps of the checking pressure :
Step
Action
Diagram
1
Disconnect the gauge (14)
0--1 MPa.
14
2
D
Remove the filling tool (2)
and re--install the plug (17), ap-
plying a tightening torque of
4 daN.m; leak--tightness is
only guaranteed if this condi-
tion is respected.
D
Screw the valve--cap (3) on
the filling tool (2).
17
2
3
Summary of Contents for FKG1X
Page 2: ......
Page 7: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 13: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 17: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 21: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 75: ...This page is intentionally blank This page is intentionally blank...