Maintenance
Maintenance plan
G51--001EN07
12/18
02--2011
© ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be
relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is
strictly prohibited.
GRID
Detail of circuit--breaker maintenance operations
, continued
Condition of crontrol
rod system
Check presence and condition of retaining clips and spacer washers on the
axles of the control rod/crank assembly.
During all dismantling of the control rod assembly, replace the retaining clips
removed by new ones of the same type. For correct orientation of clips see
section entitled : “ERECTION”.
Electrical densimeter
thresholds
Check the electrical contact SF
6
densimeter thresholds.
If the values found are outside required tolerances replace the densimeter.
Operating times of
poles and auxiliary
contacts
Measure the operating times of poles and auxiliary contacts, following proce-
dure in section entitled : ”PRE-COMMISSIONING INSPECTIONS”.
If the values found are outside those given in the document ”Acceptation Cri-
teria” contact
ALSTOM Grid S.A. Customer Service
.
Measurement of con-
tact resistance
see section “MESUARING MAIN CIRCUIT RESISTANCE”
This operation must be performed for thefirst time at factory, the values found
are taken as a reference to judge how the apparatus evolves with time.
CAUTION : BEFORE ANY MEASUREMENTS ARE TAKEN IT IS ABSO-
LUTELY NECESSARY THAT THE APPARATUS BE ELECTRICALLY AND
MECHANICALLY INOPERATIVE.
Tightening of
mountings
Check and adjust, with a torque wrench, the tightening torques of screws on
sub--assemblies not subjected to gas pressure. The tightening torques are
given in paragraph ”Tightening torques”.
Tightening
LV terminals
With the electric cubicle out of service, check that the connectors and tips of
conductors are tightened correctly and check the torque of connection mount-
ings.
Tool used : 4 mm diameter screw driver , for terminals of the ”Entrelec” type
(for example).
CAUTION : SCREWS ON TERMINALS MUST NOT BE OVER--TIGHT-
ENED.
Relay operation
Check relay operation by executing the following circuit--breakersequences :
D
closing lock--out,
D
automatic opening,
D
anti--pumping.
Continued on next page.
Summary of Contents for FKG1X
Page 2: ......
Page 7: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 13: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 17: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 21: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 75: ...This page is intentionally blank This page is intentionally blank...