Maintenance
Maintenance plan
G51--001EN07
15/18
02--2011
© ALSTOM 2010. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be
relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is
provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is
strictly prohibited.
GRID
Detail of circuit--breaker maintenance operations
, continued
Changing the FK3--12
When carrying out the 10,000 cycle servicing the circuit breaker’s FK3--12
operating mechanism should be changed. This operation must be carried out
by
ALSTOM Grid S.A., Customer Services
, who should be contacted prior
to all interventions of this type during the planning phase.
Changing
the connector
Rod assembly
When carrying out the 10,000 cycle servicing the circuit breaker’s connector
rod assembly should also be changed.
This operation must be carried out by
ALSTOM Grid S.A., Customer Ser-
vices
, who should be contacted prior to all interventions of this type during
the planning phase.
Replacement of bea-
ring motor--driven
fans
(if applicable)
In case of anomaly in the state of the bearing of the motor--driven fans, con-
tact:
ALSTOM Grid S.A., Customer Service
, in order to envisage changing the
deteriorated parts.
Summary of Contents for FKG1X
Page 2: ......
Page 7: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 13: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 17: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 21: ...GRID High Voltage Switchgear This page is intentionally blank...
Page 75: ...This page is intentionally blank This page is intentionally blank...