42
Glazing
Glass Size
Code
78 712
A
(see diag.)
EV457X496X39
6
B
(see diag.)
EV405X920X515
4
C
(see diag.)
EV405X540X135
2
D
(see diag.)
EV610X1345X838
2
E
(see diag.)
EV556X810X23
4
F
(see diag.)
EV610X725X218
2
295x916
EV295X916
4
405x916
EV405X916
4
457x916
EV457X916
6
610x916
EV610X916
2 6
610x153
610X153
4
525x100
D729TG
12
610x610
610X610
2 4
610x1256
EV610X1265
- 2
610x1345
EV610X1345
4 6
284x1050
VICG0005
(pre-installed)
2
SEPERATORS
ROSPES
(610mm)
14
GLASS STOPS
EV0313M
(aluminium)
16 24
RUBBER?
D227 = 10meters
100m 130m
Silicone
13
Standard cedar capping or the upgrade aluminium capping?
Glazing Rubber
NB:
Capping lists can be found at the
rear of this book. Use the lengths to
help identify each part.
NB:
Before you start glazing check
the squareness of the greenhouse,
installing a large roof pane will often
tell you more than a spirit level.
IMPORTANT:
It is advisable to glaze the porch roof
panes
E
first whilst the building has
maximum movement in it, they are the
panes which tend to be hardest to fit.
It is then a good idea to fit a rear side
pane to check that the structure is
vertical and a large roof pane to check
that the building is square. The roof
sheets which reach down to the eaves
bars need to be retained by a pair of
aluminium glass stops (EV0313M), see
next pages.
Your porch
gutters
need to be fitted
prior to fitting panes
D
and
F
but after
all the side panes have been installed.
The roof glass canopies the fixing
points on some of the gutter sections
so the gutters need to be fitted first.
Slide the glass
into the groove of
the eaves bar and
rest it on the
cedar mid rail.
610 x 916
Glazing Bar
Capping
If you have the Aluminium capping you
need to slide the glazing rubber into
channels on the back of the capping (see
right), this includes the porch internal
corner capping (EV1180M). Use a Stanley
knife or scissors to cut to length, it is best
to use a complete length per side.
If you have the cedar capping you can pre
load each strip with the 25mm Pan Head
screws (EV0331). Also before you install
each pane you need to run a thin bead of
silicone up each glazing bar (no greater
than 5mm is needed).
All of the capping is pre-cut to length, so
sort through it placing the capping
around the building close to were you can
reach it.