background image

11 

 

Front Assembly

 

Diagram 9 

50mm Scre

w

 

EV0070 

EV0

006

 

External 

With the parts flat on the ground drill the pilot holes 
through each mortise in the cills and as before 
through the lap joint on the gable bars.  Also drill 
pilot holes through the mortise holes on the gable 
bars ready for the door header.  Fix the front cill to 
the gable glazing bar using a 50mm screw.   
 
Slot the tennon of the front cill into the side corner 
bar as before (diagram 9). Fix this with a 80mm 
screw.  Also screw this to the base with 25mm 
screws.  Keep the gable glazing bar supported while 
you get the next parts ready.  

Dia. 9 

Part 

Number 

Size 

(mm) 

Qty 

EV0007 975  2 

EV0042 1794  1 

EV0043 1794  1 

10ft Front 

Part Name 

Front Cill 

Roof Corner R 

Roof Corner L 

Side Corner R 

EV0056 1650  1 

Side Corner L 

EV0057 1650  1 

Gable Bar 10 R 

EV0070 2136  1 

Gable Bar 10 L 

EV0071 2136  1 

Door Header 

EV0109 1276  1 

Above Door 

EV0078 486  1 

Gable Bar 6 L 

EV0061 1994  1 

Gable Bar 6 R 

EV0060 1994  1 

EV00

07 

Summary of Contents for Evolution 10

Page 1: ...11 14 Standard building Extension...

Page 2: ...ructions Contents Introduction Base Preparation Overview Base Assembly Side Assembly Front Assembly Extension Installation Rear Assembly A frame Assembly Roof Assembly Section 1 2 3 4 5 6 7 8 9 Page 3...

Page 3: ...ther vulnerable locations To minimise the risk of wind damage try to select as sheltered a site as possible e g beside a hedgerow or garden fence Additional Considerations Please bear in mind that ass...

Page 4: ...o and convenient to bring water to and possibly a supply of electricity Finally and most importantly choose a site where your Alton Greenhouse will look right so that it will complement your garden Ba...

Page 5: ...g through one piece of timber into another it is always recommended to predrill the first piece This will prevent the timber from splitting which could weaken the structure You can build the sides of...

Page 6: ...ning on a set of steps All you have left to do now is fit the gutter and downpipes think about where you might site a waterbutt when doing this You can always add a Partition or another Extension at a...

Page 7: ...holes will take a 25mm screw when the side cills are fixed to it Also fit the front door cill with 2 plates HE512 diagram 2 Use the larger plates at an extension point EV0312M diagram 3 Don t fix any...

Page 8: ...ht fit so you may need help with this or maybe use a solid object to push against Once firmly in position fix with the 50mm screw Now slot the eaves rail into position There is no need to fix this yet...

Page 9: ...ll the way in you may find they need a light tap with a wooden mallet or something similar If you are going to glue your joints this is the first point you would do this 50mm Screw Pilot hole it is ea...

Page 10: ...ch other so the screws don t intersect each other Now offer the side corner to the eaves bar slotting the tennon into the mortise shown in diagram 5 do not fix this joint as it will be done at a later...

Page 11: ...tennon of the front cill into the side corner bar as before diagram 9 Fix this with a 80mm screw Also screw this to the base with 25mm screws Keep the gable glazing bar supported while you get the ne...

Page 12: ...nal Drill through the bottom of the tennon in the door header EV0109 then fix the glazing bar above the door with a 50mm screw 50mm Screw EV0109 EV0078 Diagram 10 EV0070 EV0109 50mm Screw External Dia...

Page 13: ...ars to the front end As before fix the lap joint at the top of the gable bar first with 40mm screws diagram 17 then secure the bottom end to the eaves bar with a 80mm screws diagram 18 Diagram 12 Inte...

Page 14: ...aluminium base and slide it up to the forst side section until the tenon slots into the mortise joint With help or the aid of a prop screw the cill to the base using 25mm screws Diagram 14 Diagram 15...

Page 15: ...cill Slot the top into position lining the edge of the bar up with the joint of the two eaves bars Secure this with a 50mm screw and the secure the bottom with a 40mm screw remember to drill a pilot h...

Page 16: ...s Don t fix the top of the bar until the roof corner bars have been fitted Part Number Size mm Qty EV0012 3106 1 EV0042 1794 1 EV0043 1794 1 10ft Rear Part Name Cill Roof Corner R Roof Corner L Side C...

Page 17: ...he cill section through the mortise holes as before diagram 18 Also drill 2 holes in the top of the gable glazing bars through the lap joint location These should be 25 30mm apart and the first hole s...

Page 18: ...lazing bars diagram 19 Now fix the roof corner bar and side corner bar through the eaves bar with an 80mm screw You can then screw the base to this section with a 25mm screw EV0061 EV0043 40mm Screw E...

Page 19: ...me next Take the eaves extension braces and locate them in the mortise slots in the extension side bars Pilot hole and fix these with 40mm screws Make sure the flat face that meets the side bar is sea...

Page 20: ...am 22 Before fixing these it would be a good idea to fit the A frame brace diagram 24 Once these are all in place check they are all inserted correctly and fix them with 40mm screws Dia 22 Dia 23 Don...

Page 21: ...21 A frame Assembly 8 Diagram 24 Dia 24 EV0188 40m m Screw 40m m Screw E V 0 1 8 1 EV0191 EV0191 EV0188 Note For a neater finish insert the screws in the rear of the bar...

Page 22: ...ce these about 50 60mm apart with an 80 90mm gap in the middle so that the fixing screws don t interfere with the ridge joint Fix this the extension ridge while on the ground Lift it into position and...

Page 23: ...through the top face of the roof corner bars This is to prevent the end or the screw coming through the bottom of the roof glazing bar This angle will also give a much better and stronger fixing Diag...

Page 24: ...e main ridge section locate this with the roof corner bars on the front of the building Fix this as before and then fix the ridge plate to the main ridge as shown in diagram 25 with 80mm screws Dia 29...

Page 25: ...25 Roof Assembly 9 Now the ridge bars are installed you can return to section 7 on page 19 of your main book to complete the assembly of the building...

Page 26: ...26 Notes...

Page 27: ...27 Notes...

Page 28: ...Alton Greenhouses TGP Ltd Blythe Park Cresswell Stoke on Trent ST11 9RD Telephone 01782 385 409 www Altongreenhouses co uk sales altongreenhouses co uk...

Reviews: