To start building your greenhouse begin by laying out the components for your sides flat on the
ground like the diagram below. Use the tables below to identify your building length and the
components with the part numbers and sizes. First of all drill pilot holes through the bottom of each
mortise on the cill section (diagram 3, page 9). Then slot each glazing bar into the mortise holes.
These are designed as a tight fit so you may need help with this or maybe use a solid object to push
against. Once firmly in position fix with the 50mm screw. Now slot the eaves rail into position (e.g.
EV0021). There is no need to fix this yet as it is done at a later stage.
Side Assembly
4
Part
Number
Size
(mm)
Qty
EV0015 1846 2
EV0020 1934 2
EV0030 1588 4
6ft
Part Name
Cill
Eaves Bar
Glazing Bar
Part
Number
Size
(mm)
Qty
EV0014 1216 2
EV0019 1304 2
EV0030 1588 2
4ft
Part Name
Cill
Eaves Bar
Glazing Bar
Part
Number
Size
(mm)
Qty
EV0016 2476 2
EV0021 2564 2
EV0030 1588 6
8ft
Part Name
Cill
Eaves Bar
Glazing Bar
Part
Number
Size
(mm)
Qty
EV0017 3106 2
EV0022 3194 2
EV0030 1588 8
10ft
Part Name
Cill
Eaves Bar
Glazing Bar
Part
Number
Size
(mm)
Qty
EV0018 3736 2
EV0023 3824 2
EV0030 1588 10
12ft
Part Name
Cill
Eaves Bar
Glazing Bar
EV0016
EV0021
EV0030
Dia. 3
Dia. 4
EV0030
EV0030
example
Internal