background image

 

2/13/2012 

Page 8

TRAILER TOWER SETUP INSTRUCTIONS-GUYED TO OUTRIGGERS

 

 

3. 

Remove guy wires from anchors while still in vertical position. 

 
4. 

Remove the nut from the latch bolt on tower lockdown bar. Be sure to retighten 

 

the nut with a wrench so that it will not vibrate loose while transporting. Push the 

 

tower away from the trailer while playing out the cable from the winch. 

 
Sufficient load must be applied to the cable to overcome internal resistance and operate 
brake properly. NEVER CONTINUE TURNING THE HANDLE COUNTER-
CLOCKWISE IF THE CABLE DOES NOT KEEP MOVING OUT. This will disengage 
the brake mechanism and create an unsafe or hazardous condition. MINIMUM 
OPERATING LOAD REQUIREMENTS - Model 5351 -  75 lbs. 

Failure to read and apply the instructions and warnings contained in this 
manual can result in sudden failure of equipment, property damage and 
serious injury. 

 
5. 

Lower the tower to the horizontal position and secure the tower with the hold 

 

down cable. Be sure locking mechanism on cable is engaged. Remove the coax 

 

cable, antenna, guy wires and put mast in towing position. 

 
6. 

Remove all guy wires and carefully coil and return them to their color-coded 
pouches. If you choose to remove the Duck Bill ground anchors this can be 
readily accomplished by digging straight down over the head with a post hole 
digger or shovel and then pulling back on the eye towards the hole. 

 
7. 

Raise the front leveling jacks until the weight is on the tongue jack. Remove the 

 

front leveling jacks and stow them in the storage box. 

 
8. 

Remove the rear outrigger leveling jacks and stow them in the storage box. 

 

Remove the hitch pins from the outriggers and slide them in to their stowed 

 

position and reinsert the hitch pins. 

 
9. 

You are now ready to hook up the trailer to the tow vehicle. Once again recheck 

 

all securing straps and safety wires. Repeat procedure for 

“Getting ready to 

 

transport”. 

 

 

If you choose to guy trailer tower unit model number S6, S7, S8, or S812 with 
“XXHD”, “XHD” or “H” series towers to the outriggers please follow these 
recommendations (See Aluma Drawing QS-1848 below for details): 

a)

 

Slide out the two front and two rear outriggers, connect the leveling 
jacks to outriggers, and use them to level out the trailer. 

b)

 

Inspect all pulleys and cables.  Make sure cable is running in the center 
of every pulley sheave.  Remove front upright and shelter safety 
straps. 

c)

 

While the tower is in the stowed/horizontal/transportable position, use 
shackles to connect red guy wires or guy wires for the top section to 
the guy ears located at the top of the top tower section.  The red or top 
section should contain 4 guy wires.  Make sure that the tower legs that 
are attached to the shelter receive individual guy wires.  Attach a 
shackle to the leg of the tower furthest from the shelter and connect 
two guy wires to that single shackle.  

d)

 

Remove nuts from latch bolts at the bottom rear of the trailer chassis.   

Summary of Contents for TM-12

Page 1: ...s Includes Guying to Outriggers To be used for the following trailer models TM 12 TM51WA35 EB4S6 TM51 20LT TM52WA60 EB4S7 TM51 35 TM61WA80 EB4S8 TM52 60 TM61WA812 EB4S812 Aluma Tower Company Inc 1639...

Page 2: ...RNINGS NEVER setup the tower within 120 feet of a power line NEVER attempt to climb your tower under any circumstances Always lower tower completely and access your tower by use of a suitable ladder T...

Page 3: ...ORE transporting trailer tower check to see that both the tower hold down cable and the Red Strap at the rear bottom end of the tower are in place and secure WHEN transporting trailer and tower drive...

Page 4: ...concrete type ground anchors can be used Fig 4 Standard Guy Wire Anchor Points 2 The tow vehicle must now be uncoupled from the unit Remove the safety pin and unlatch the coupler Either swivel and loc...

Page 5: ...he Tower Models T BD 35H T BD 50H T 50H T 50XHD T 50XXHD T 75H T 75XHD T 85UGH T 100H T 100UGH Remove the thru bolts from the upper and lower mast adaptor plates Insert mast through upper plate mast a...

Page 6: ...eep the cable properly seated on the sheave and keep the pulleys from being damaged ERECTING THE TOWER AT FULL HEIGHT 1 While the tower is still in the horizontal position loosen and remove the hold d...

Page 7: ...that the tower is as level and plumb as possible If tower is not level readjust the jacks on the trailer to re level trailer 5 IMPORTANT Undo the Red Safety strap from the bottom of the tower and remo...

Page 8: ...ing the tower when the top guy wires become taut Do not over extend the tower 2 For the Tower Models having 4 sections Attach the green color coded ends of the guy wires to the corresponding green col...

Page 9: ...back on the eye towards the hole 7 Raise the front leveling jacks until the weight is on the tongue jack Remove the front leveling jacks and stow them in the storage box 8 Remove the rear outrigger l...

Page 10: ...uy wires attached to the single tower leg furthest from the shelter to the two rear outriggers Apply approximately 100 lbs of pretension to each guy wires and tighten the cables on the turnbuckle Plea...

Page 11: ...FERENCE TO ORANGE REFLECTIVE TAPE ON SAFETY STOP RUNG ALSO CHANGED NYLON CORD TO ORANGE CORD FOR SAFETY STOP DISENGAGEMENT DECEMBER 18 2007 ADDED ALWAYS TOW LEVEL ALWAYS INSURE VEHICLE HITCH ARE PROPE...

Page 12: ...T 85UGH T 100UGH TOWERS APRIL 17 2009 ADDED INSTRUCTIONS ON GUYING TO THE OUTRIGGERS WITH THE TOWER ERECTED AT 70 FOR ALL SHELTER TRAILERS WITH H XHD OR XXHD SERIES TOWERS JANUARY 5 2010 ADDED INCLUDE...

Reviews: