Supervisor 2000 Installation Instructions
PUD1601R6-1
For Assistance: support@alvaradomfg.com +1 (909) 591-8431
Page 17
Anchoring the Turnstile (cont.)
3. Use a pencil and mark each anchor hole location
[Figure 16]. There will be a total of two (2) anchor
holes per cabinet. Remove the cabinets when
complete.
4. Using a 1" concrete drill bit, drill the anchor holes 3"
in depth at the center of each marked location.
The anchor holes must be clean before installing the
anchor bolts. If the holes are not clear of debris, the
anchor bolts may not tighten correctly.
5. Insert the anchors into each drilled hole [Figure 17].
The threaded end of the anchor must be inserted into
the hole first. Use a rubber mallet to tap the anchors
into place, if needed. Ensure that the anchors are
flush with the concrete floor.
6. If not already done, pull all wires (AC power, access
control and crossover cable) through conduit and
conduit access holes prior to anchoring cabinets.
7. Using clear RTV silicone, seal the gaps between the
conduit and conduit holes.
8.
Maneuver each cabinet over the anchor locations.
Insert two (2) 5/8" anchor bolts and flat washers.
9. Using a torque wrench (ft-lb) and 15/16" socket,
torque the anchor bolts to 60 ft-lbs.
NOTE
Anchor
Holes
Marking Anchor Holes
Figure 16
Anchoring
Figure 17
Concrete Anchor