Supervisor 2000 Installation Instructions
PUD1601R6-1
For Assistance: support@alvaradomfg.com +1 (909) 591-8431
Page 19
Crossover Cable
The included crossover cable interconnects communication signals
and low-voltage power between the master and slave cabinets.
The default length of the crossover cable included with the SU2000
is 11'. Optional crossover cable lengths of 20' and 40' are available.
1. Connect one end of the crossover cable to the connector
tucked into the master cabinet as shown in [Figure 19].
2. Connect the other end of the crossover cable to the slave
cabinet status light board as shown in [Figure 20].
Wiring Instructions
IMPORTANT
110VAC and 220VAC primary power (unless ordered otherwise)
must be hard wired in place. It is strongly recommended that a
licensed electrician perform this procedure in accordance with
all applicable local codes.
The primary wiring lines for 110VAC and 220VAC consist of the
following:
Terminal
110V
220V
G
round
Green
Green/Yellow
N
eutral
White
Blue
L
ine
Black
Brown
1. Locate the pre-installed power terminal block and attached
wiring (located inside the master cabinet leg) [Figure 19].
2. Attach each primary power wire to the power terminal block
with the corresponding color exiting on the other side
[Figure 19A].
3. Using a Phillips head screwdriver, tighten each terminal
block connection.
Primary Power
The orientation of the pre-installed terminal block may differ
from what is shown in [Figure 19 & 19A]. On some installations,
the terminal block is rotated 90 degrees .
NOTES
220VDC Shown
Crossover Cable
220VDC Power
Cable Shown
Primary Power and Crossover Cable
(Master Cabinet)
Figure 19
Crossover Cable Connection
(Slave Cabinet)
Figure 20
Figure 19A
Crossover
Cable
Status Light
Board