Operation
2110A PT Peanut Combine
Daily Pre-Start Check
Perform these daily pre-start checks each day
before taking the machine to the field. The
pre-start check will help detect problems
early, reduce downtime, and extend the life of
your combine.
1. Service the tractor and attach the
combine.
2. Grease the PTO driveline as shown in the
sketch (also see Lubrication Chart in
Chapter 7,
Maintenance
).
3. Check all hydraulic lines for proper
connection.
4. With adequate overhead clearance, lift the
bin to a fully raised position.
5. Put the tractor in park, shut off the engine,
and remove the key.
6. Lock the bin in the fully raised position
with the safety strut (photo).
7. Inspect the combine for broken parts
and wear.
8. Inspect the cylinders and adjustable bars
for damaged or broken spring teeth.
Also inspect for metal, wood, or other
foreign material lodged within the picking
chamber.
9. Remove vines wrapped around the
spring tooth cylinder and beater cylinder
shafts.
10. Remove any foreign material found;
replace any missing or damaged spring
teeth.
DANGER
Check overhead clearance to ensure that
no power lines, overhead limbs, or any
other obstructions exist. The combine
exceeds 13’-10” with the basket lowered.
When fully raised, the AMADAS 2110A
stretches over 24 feet tall. Contact with
an obstruction or high voltage power line
could result in death or serious personal
injury.
CAUTION
ALWAYS install the safety strut over the
hydraulic cylinder before working under
the basket. Death or serious personal
injury can result if the bin falls.
NOTE!
Continued operation with missing
or damaged spring teeth may reduce
picking efficiency and reduce service life
of adjacent spring teeth.
30
12/21/15
MAN143
Summary of Contents for 2110A
Page 2: ......
Page 4: ......
Page 22: ...Safety 2110A PT Peanut Combine 4 80945 6 80947 5 80946 12 12 18 15 MAN143...
Page 23: ...2110A PT Peanut Combine Safety 7 80949 8 80950 11 80936 9 80941 10 80563 MAN143 12 18 15 13...
Page 32: ...Preparation 2110A PT Peanut Combine NOTES 22 2 29 16 MAN143...
Page 56: ...Unloading Conveyor 2110A PT Peanut Combine NOTES 46 12 18 15 MAN143...
Page 78: ...Performance 2110A PT Peanut Combine NOTES 68 12 18 15 MAN143...
Page 91: ...2110A PT Peanut Combine Maintenance NOTES MAN143 12 18 15 81...
Page 92: ...Maintenance 2110A PT Peanut Combine NOTES 82 12 18 15 MAN143...
Page 98: ...Peanut Tech Monitoring and Control 2110A PT Peanut Combine NOTES 88 12 18 15 MAN143...