Structure and function
78
Primera BAG0175.3 07.18
5.21.1.1 Examples for creating tramlines
The creation of tramlines is shown in Figure (Fig. 68) using various
examples:
A =
Working width of the seed drill
B =
Tramline spacing (= working width of fertiliser spreader / field
sprayer)
C =
Tramline rhythm (input in the on-board computer)
D =
Tramline counter (during work, the field runs are numbered
consecutively and displayed on the on-board computer).
Perform any inputs and outputs with the aid of the on-board computer
operating manual.
Example:
Working width, seed drill: 6m
Working width, fertiliser spreader/field sprayer: 18m = 18m tramline
spacing
1. Look for the following in the adjacent table (Fig. 68):
in column A, the seed drills working width (6 m) and
in column B, the tramline spacing (18 m).
2. On the same line in column "C", take the reading for the tramline
rhythm (tramline rhythm 3) and set this in the on-board comput-
er.
3. On the same line in column "D" under the inscription "START"
take the reading of the tramline counter for the first field run
(tramline counter 2) and enter this figure on the on-board com-
puter. Input this value directly before commencing the first field
trip.
Summary of Contents for DMC 6000-2
Page 60: ...Structure and function 60 Primera BAG0175 3 07 18 Row spacing 25 cm ...
Page 79: ...Structure and function Primera BAG0175 3 07 18 79 Fig 56 ...
Page 134: ...Cleaning maintenance and repairs 134 Primera BAG0175 3 07 18 Fig 115 ...
Page 157: ...Cleaning maintenance and repairs Primera BAG0175 3 07 18 157 12 12 Hydraulics diagram ...
Page 158: ...Cleaning maintenance and repairs 158 Primera BAG0175 3 07 18 Hydraulic brake Fig 136 ...
Page 160: ...Cleaning maintenance and repairs 160 Primera BAG0175 3 07 18 Fan hydraulic system ...
Page 162: ......