GreenDrill 5.2 on-board computer
GreenDrill BAH0054-4 02.13
55
7.7.2.2
Cable set with 3-pin standard socket for the battery connection
The cable set (optional) with 3-pin standard
socket is used for power supply if the tractor has
no 3-pin standard socket. The cable ends are
screwed directly onto the battery poles.
Interface (1): 12 volt (cable colour red)
Interface (2): 12 volt (cable colour red)
Interface (3): Ground (cable colour black)
7.7.3
Connection to the 12-pin signal plug of the on-board computer
The on-board computer requires 3 signals
Travel speed [km/h]
The machine is in working position
The machine is in transport position.
The on-board computer shows the tractor's speed [km/h] and adjusts the sowing shaft speed accord-
ing to the changing tractor speed. The sowing rate remains unchanged even at varying tractor speeds.
If it is set correctly, speed differences of 50% are adjusted up or down.
When the implement is raised (lifting gear signal), e.g. when turning at the end of the field, the sowing
shaft remains still. Manual operation of the on-board computer is not possible for the tractor driver.
Turning at the end of the field is automatic.
On some tractors, the lifting gear signal is inverted. The lifting gear signal can, when required, be
turned around in the on-board computer (see Chapter "Lifting gear sensor").