4.5.5 Mechanical installation of Pacific 300 mizzen bracket
The major load that the bracket has to withstand is one of torsion, hence the box section. At 100mm wide
this is close to the width of many mizzen masts and any slight difference can be accommodated by
bending the end plates to suit or by spacing with nuts and washers.
Drill through the end plates and mizzen and fit using the M10 fixings provided. Monel rivets are the best
attachment method for aluminium masts. Studs are best for wooden masts. If using studs on aluminium
masts then fit spacers so as not to crush the mast.
If there is any danger of running rigging becoming entangled in the wind turbine then install stays to keep
the turbine guarded.
4.6 Electrical installation
Electrical installation should only be performed by competent personnel who have studied this manual. If
in doubt ask Ampair.
First mechanically mount the main system components (except the wind turbine), then run the field
cabling, then make the connections, then install the wind turbine and connect to it. Only then connect to
the battery.
WARNING:
Do not assemble the generator, vane and turbine until the electrical installation is
completed
4.6.1 Wiring diagrams
4.6.1.1
Wiring diagram without regulator
rectifier
battery
+
-
stop
switch
fuse
ammeter
DC colour code:
Red = positive (+)
Black = negative (-)
Fuse sizing:
30 A for 12 V
15 A for 24 V
Block diagram
alternating current, AC
direct current, DC