Installation
5
6" Color Video Touch Panels
Installation
Installation of the Conduit Box
Wall Mount panels (AXDs) are contained within a metallic outer housing (back box). This back
box is not removed when installing the AXD into a conduit box (CB-CV6).
1.
Fasten the CB-CV6 to the stud through the tabs shown in FIG. 3. The wallbox can be secured
to the stud by using either nails or screws. This installation must be done prior to any wall
installation.
2.
Remove any necessary wiring knockouts from the (optional) conduit box where the necessary
cables are threaded through for connection to the touch panel.
3.
Thread the incoming wiring through the knockouts. Leave enough slack in the wiring to
accommodate any re-positioning of the panel.
4.
Install the drywall/sheetrock before inserting the main AXD unit into the CB-CV6.
If installing the CB-CV6 into an pre-existing wall or surface, use the following cutout
information (FIG. 4
)
(found online at
www.amx.com
using drawing number
SP5924-02
).
INSTALLER: LEAVE A GAP BETWEEN THE STUD AND CONDUIT BOX TO
ACCOMMODATE THE DRYWALL SHEETROCK. T
his gap allows the installation of
the drywall/sheetrock after the conduit box has been installed.
FIG. 3
Screw location for CB-CV6 conduit box attachment in a pre-wall installation
Sheet
rock
Stud
Tabs may be removed if not used for the installation
CB-CV6 Conduit Wallbox
TYPICAL DRYWALL INSTALLATION
Mounting tabs
for AXD panel should
be flush with the outside of the sheetrock
Stud fastening holes
Knockouts