Step 7 - Fabric Tensioning

• 

At back of pavilion, snap buckles of back-end straps to corresponding buckles at bottom of mids.  Insert bottom hook into 
slot at back of upright.  Tighten just enough so that hook does not fall out of slot.  (Figure 7a)

• 

At front of mids, insert tension tubes into pockets under curtain.  Between mids, use a tension tube splice to connect 
tubes.  (Figure 7b)  Before insertion, hang tension strap with ratchet and hook over the tension tube splice.  At ends, hang 
tension strap over end of tension tube as shown in Figure 7c.

• 

Insert hook of tension strap into slot in front upright.  Crank ratchet until tension strap stays in place but do not tension.  
Check mids to be sure they are all pulled to the same point in front and back.  Check back end straps to be sure they are 
tightened uniformly.  When you have checked these things, you may now ratchet the front tension straps.  Tighten until all 
mids are uniformly snug.

Figure 7c

Tension strap over end 
of tension tube at front 
corner.

Back View

Mid Fabric

Mid Fabric

Rear Corner Up-
right

Rear Upright

Slot in upright

Slot in upright

Use single back 
end strap at corner 
upright.
Connect male buck-
le to female buckle 
at bottom of mid.

Use double back 
end strap at 
uprights between 
mids.

Figure 7a

Frame attaching 
bracket

Frame attaching 
bracket

TENSIONING 

TUBE SPLICE

TENSIONING TUBE

Figure 7b

Inside view looking at tension 
pocket under curtain.

Tension Pocket with 
tension tube inserted.

Tensioning Tube Splice 
is used between mids 
fi ts into ends of tension 
tubes.

Summary of Contents for Navi-Trac LT/CS

Page 1: ...instructions before the installation or removal of this product Installation Instructions Navi Trac LT CS Pavilion 12 to 24 Projection 7701 Highway 41 N Evansville IN 47725 Phone 812 867 2421 Fax 812...

Page 2: ...er lines near the site 5 When anchoring the structure avoid all underground power lines and gas lines or other utility easements 6 Keep site clear of debris to avoid tripping especially while carrying...

Page 3: ...10 0 PURLIN NAVI TRAC 80410 2 1 2 1 2 1 2 1 2 1 MID TENSIONING TUBE 80779 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 MID TENSIONING TUBE SPLICE 80780 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 CONTAINER 1 BASE PLATE ADJUST...

Page 4: ...PROJECTION END UPRIGHT EAVE WELDMENT RIDGE WELDMENT RWP EAVE END R L WELDMENT RIGHT SHOWN EPR EAVE WELDMENT EWP EPL LEFT OPPOSITE SHOWN FRAME ATTACHING BRACKET BASE PLATE ADJUSTABLE 4 HOLE BAP BA BAS...

Page 5: ...PROJECTION E10 EAVE SLIDE IN U 8 UPRIGHT 8 RP 22 RAFTER 22 PROJECTION RAFTER X CABLES EPL END LEFT WELDMENT NOTE UPRIGHTS ARE 8 TO 10 AD JUSTABLE HEIGHT EAVE WELD MENT EWP BAP BASE PLATE ADJUSTABLE 4...

Page 6: ...ructures above 20 projection 2 Hole Base Plate required at this position only LAYOUT DIMENSIONS Pavilion Size A Dimension B Diagonal Dim 12 Projection x 30 12 6 15 16 32 6 3 8 14 Projection x 30 14 6...

Page 7: ...eye bolt with eye nut not usual On rafters with no X cables attach the rafter using the pin attached to the ridge weldment 6 On frames with 20 projection or more rafter brace is now attached to trian...

Page 8: ...a Turnbuckles should be open all the way Figure 3a First beam arch as sembled and raised Note Turnbuckles at free end Eyenuts on inside of Rafter Eyenuts face ground on sec ond rafter Eyenuts on insid...

Page 9: ...lace stabilizer plate washer and hex nut back onto rod so that bracket stays in place Do not tighten until frame and fabric are completely assembled and in stalled Do not use stabilizer plate at corne...

Page 10: ...dment Figure 4d Purlin Drop curved end of purlin into rafter bracket See figures 4e and 4f Drop square hook end into the correspond ing rafter bracket Note If optional installation kit has been used r...

Page 11: ...annel on Upright Rear Upper Splice Feed both kedars down at the same time and at the same time until kedars are fully inserted into channels Fig ure 5b Continue this process until all mids are install...

Page 12: ...Rear Upper Splice Figure 6b After end fabric is in place fiesta buckles on inside of fabric at eave must be con nected Slide kedar pieces with d ring into top outside channel of eave beam Align these...

Page 13: ...n Check mids to be sure they are all pulled to the same point in front and back Check back end straps to be sure they are tightened uniformly When you have checked these things you may now ratchet the...

Page 14: ...ction to existing building must be determined by cus tomer Step 8 Fastening Frame to Existing Building At back of pavilion adjust the frame attaching bracket so that is is fitted up to existing buildi...

Page 15: ...15 Notes...

Page 16: ...vided in the installation instructions is not a suggestion about what is necessary to meet a site specific load For additional important information consult The IFAI Procedural Handbook For the Safe I...

Reviews: