5.0 COMMISSIONING GENERAL
After installation of pipe work and fi ttings the water systems can then be fi lled and evacuated of all air before
commissioning the heat engines using gas can commence.
5.1 FILLING AND REMOVAL OF AIR
5.1.1 DHW TANK AND SYSTEM
In order to ensure safe removal of air from the hot water system, please perform the following:
1. Check that the tank drain shut off valve is closed.
Tank drain shutoff valve
2. If the appliance is connected to a hot water recirculation system, open the isolation valve immedi-
ately before the connection point to the tank.
3. Turn on the entire hot water draw off taps.
4. Turn on the cold water supply and fi ll the DHW tank.
5. Close each hot water draw off tap when water is discharged.
6. After initial fi lling, open each hot water draw off tap in succession and check that all the air is
vented from the system.
7. Check for leaks inside and outside of the appliance.
5.1.2 PRIMARY SPACE HEATING CIRCUIT (FILLING AND BLEEDING)
The heat engines and Low Loss Header (LLH) must be completely full of water and devoid of all trapped air.
Failure to remove air from the heat exchangers can result in permanent damage and failure of the appliance.
Fill / drain point
Pressure relief valve
Summary of Contents for COMBIflo 100/300
Page 9: ...ANDREWS COMBIflo 7 GB 3 1 GENERAL DIMENSIONS CONNECTIONS 3 0 TECHNICAL DATA ...
Page 12: ...ANDREWS COMBIflo 10 GB 3 4 APPLICATION EXAMPLES Single Heating Circuit Simple ...
Page 13: ...ANDREWS COMBIflo 11 GB Single Heating Circuit Immersion DHW Circulation pump ...
Page 16: ...ANDREWS COMBIflo 14 GB Heating Circuit External 0 10V control ...
Page 17: ...ANDREWS COMBIflo 15 GB BMS INTERNET CONNECTIONS ...
Page 18: ...ANDREWS COMBIflo 16 GB 3 5 WIRING DIAGRAMS PCB 1 ...
Page 19: ...ANDREWS COMBIflo 17 GB PCB 2 3 ...